Whittier Elementary School
2008 Pine Street Boulder, CO 80302 | 720.561.5431
Original Construction Date | 1882
PHASE
Phase 3
PROJECT BUDGET
$1,466,951*
*Final budget will be determined during the design phase.
View Project Expenditures
PROJECT TEAM
PROJECT MANAGER: Gene Temanson
ARCHITECT: BVH Architects
CONTRACTOR: A.D. Miller Construction
ARCHITECT: BVH Architects
CONTRACTOR: A.D. Miller Construction

UPDATES
July 2026
Welcome to the July Construction Update for Whittier Elementary School! We hope summer is in full swing for you and your family, as it certainly is from our side of the fence, with plenty of work ahead from now to August. With a good portion of the summer behind us, we are pleased to report that the Whittier project is rolling along smoothly as we work toward substantial completion on Aug. 1 in time to welcome staff and students back to the building. Construction activity planned for the month of July is detailed below:
- Complete replacement and repairs to select areas of the roof
- Continue replacement of flooring in select areas of the hallways, cafeteria and kindergarten classrooms
- Begin, and complete, demolition and repaving of the main parking lot on the southwest side of the school building
There are exciting changes coming to Whittier, and we sincerely appreciate your patience as we work through the end of this summer project. Note that the school, and parts of the grounds, are still an active construction site. Thus, for the safety of everyone, we ask that you avoid coming to the campus unless absolutely necessary. The Boulder Valley School District is extremely grateful for the support given to us by the voters, and we strive to be good stewards in providing the best academic environments possible to support our students. Go Whittier!
Previous Updates
- May 2026
- April 2026
- January 2026
- September 2025
- April 2025
- February 2025
- January 2025
- December 2024
- September 2024
- December 2023
- January 2023
- June 2026
May 2026
May 2026
We hope this has been a successful school year for you and your student(s)! The BVSD Bond team is excited to let you know construction will be starting soon for renovations provided by the Building for Student Success program. These improvements are coming to Whittier Elementary School thanks to support from the entire BVSD community through passage of the 2022 Bond measure.
In addition to much-needed repair and upgrades to building systems and finishes, highlights of the improvements coming to Whittier include:
- Repair/replace areas of roof and roof components
- Concrete and paving repairs and replacement
- ADA improvements, including replacing the wheelchair lift
- Improvements to interior finishes such as flooring, ceiling tile, and paint
The full scope of work can be found on the BVSD Building for Student Success website at Whittier Elementary School project page.
Our $1.4 million project will begin after the students leave in May and will be complete when school resumes in August.
Student and staff safety is our top priority at Whittier Elementary School and in the Boulder Valley School District. During the summer months, there will be no access to the building and school grounds. For everyone’s safety, please comply with all posted signage and temporary barriers.
All workers who are authorized to be on-site will have numbered project stickers on their hard hats and will have background checks. Generally, there should be no reason for workers to interact with school staff or community members during this project.
We want to keep you informed as the project progresses. We will meet weekly with the architect(s) and construction company and will update you regularly about construction progress during the summer months. Project information, including monthly construction updates can be found on the Whittier Elementary School project website. Specific questions should be directed to me, Gene Temanson at 720-561-5951 or gene.temanson@bvsd.org.
As always, we are extremely grateful to BVSD taxpayers for this project and to you for your continued support of Whittier Elementary School. We hope you share our excitement for the great changes happening here.
Sincerely,
Gene Temanson
BVSD Project Manager
--------------------------------------------------------------------------------------
May 2026
Project postcards were sent to neighbors this month.

April 2026
January 2026
September 2025
September 2025
The project teams are in the final stages of design for the Phase 3 projects. Construction documents will be issued in the fall and the contractor’s guaranteed maximum price (GMP) will go to the Board for approval in November. Construction is expected to kick off in May 2026 after the students leave for summer break.
April 2025
February 2025
January 2025
December 2024
September 2024
December 2023
January 2023
June 2026
June 2026
Welcome to the June Construction Update for Whittier Elementary School! With school officially over for the year and students and staff off for a well-earned summer break, construction at Whittier is well underway. To allow the contractor to make the most of the summer “down time,” the school building, along with select spots around the campus, are closed to anyone besides construction personnel. This will be the case for the duration of the summer. Below is an overview of the construction activities that will be taking place throughout the Whittier campus during the month of June:
- Begin work on replacing portions of the roof (approximately a third of the surface area)
- Begin/complete demo of the parking lot and being rehabilitation of the surface
- Begin removal and replacement of flooring by kindergarten classrooms
- Begin demolition of old water heater
While the majority of the surrounding campus is accessible to the public, we ask that you and your students avoid coming to the school building itself unless specifically authorized to do so. We are very excited about the changes in store for Whittier and sincerely appreciate your patience and support as we work our way through this busy summer of construction. We hope you are having a wonderful and relaxing start to your summer break!
COMMUNITY ENGAGEMENT PROCESS
Community Engagement
To ensure the school community is engaged in the project, the project manager (PM) will work directly with the school principal to discuss the identified renovations, meet with the architect, and coordinate the construction schedule. The principal will decide which school staff or parents might need to be involved with the design process depending on the scope of work. The project manager will share information with the entire school staff at key milestones through the design process.
SCOPE OF WORK
BUILDING ENVELOPE
-
Repair/replace deteriorating areas of roof and roof components
-
Re-caulk and repair exterior masonry
BUILDING SYSTEMS
-
Repair/replace deteriorating HVAC and plumbing system components to avoid potential system failure
-
Update obsolete HVAC controls
INFRASTRUCTURE/SITE
-
Repair/replace irrigation system components
-
Repair/replace concrete and paving
-
Replace shade structure
SAFETY/CODE
- Address various ADA issues
INTERIOR SPACE IMPROVEMENT
-
Improvements to interior finishes such as flooring, ceiling tile, and paint
-
Replace wheelchair lift