University Hill Elementary
956 16th Street Boulder, CO 80302 | 720.561.5416
Original Construction Date | 1905 (Intermediate), 1949 (Primary)
Phase 1
PROJECT BUDGET
$859,897*
*Final budget will be determined during the design phase.
View Project Expenditures
PROJECT TEAM
ARCHITECT: BVH Architects
CONTRACTOR: Taylor Kohrs
UPDATES
September 2024
This project is substantially complete and students and staff are enjoying the building improvements and renovated gymnasium! The project team is working with the contractor to finalize punch list items.
Previous Updates
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- February 2024
- September 2023
- December 2023
- July 2023
- May 2023
August 2024
August 2024
Welcome to the August Construction Update for University Hill Elementary and the playground areas. As we fast approach the return of staff and students, all the projects around the school (except the AV system in the gym) have been completed. Staff and students will return to a school with a significant number of improvements inside and outside—highlights include removal of carpet from the walls in the gym and new paint, repair to outside masonry, new paint and artificial turf on the intermediate playground and drainage improvements at the primary building.
Below is a short list of activities that will be taking place during the early part of August:
-
Final inspections in select areas of work around the school and site
-
Final clean in gym
-
Demobilization of site fencing and other construction materials
-
Installation of AV equipment in gym (September)
We are extremely excited for the changes that have been made here at Uni Hill this summer, and we hope you and your student(s) feel the same way. Thank you for all your patience and support for this project and we look forward to seeing you for the start of the 2024-25 school year!
July 2024
July 2024
Welcome to the July Construction Update for University Hill Elementary and the playground areas. Several smaller projects are taking place throughout the building this month and you can expect to see an increase in construction related activity both inside and outside the school. The project is currently on schedule, with a completion date slated for early August. Below are highlights of work planned for July:
-
Complete rebuild of east stairs
-
Complete turf replacement at playground area
-
Install new flooring transition strips
-
Complete installation of new water pumps
-
Complete install of rails, acoustical panels and impact panels at the gym area
We are excited for the many changes that are coming to Uni Hill this summer. As always, none of this would be possible without your support via the 2022 BVSD Bond Program. We appreciate your patience this summer as we work to make Uni Hill the best school possible for your students to learn and grow!
June 2024
June 2024
Welcome to the June Construction Update for University Hill Elementary School. We want to congratulate you and your student(s) on another successful year at Uni Hill and hope that this message finds your summer off to a great start! As mentioned in the previous “kick-off” letter, construction activity around the school has ramped up considerably since the Memorial Day weekend with a number of trades professionals, making their way around the building and site, completing a plethora of tasks. A reminder that the school will be an active construction site, and as such, will have very limited access to both the schools themselves and the playground areas. Work planned for June is detailed below:
- Begin repairing exterior masonry in selected areas
- Complete work on select areas of the roof, including installing guardrails and downspout extensions
- Begin work on playground areas, including sandblasting existing paint, laying out templates, and repainting existing play areas
- Replace existing sidewalks in selected areas.
- Remove existing backstops and replace with new soccer goals
- Reseed grass fields
- Remove, regrade, and reinstall existing playground turf
- At the Primary Building: Demo, regrade and replace concrete on the west side. Demo and replace fencing at the drop-off area
- Replace select doors in main building
- Water pump renewal and replacement
- Main gym: protect floors, remove existing carpet and adhesives and prep for finishes
May 2024
May 2024
Our $772,000 project will begin immediately after Memorial Day weekend (with some site mobilization taking place in the days leading up to the end of school) and will be substantially complete by early August. Highlights of the project include:
-
Gymnasium upgrades, including new acoustical treatment, removal of existing carpet within this space and select finishes improvements
-
Replacement of the sound system in the gymnasium
-
Sump pump replacement and other select mechanical upgrades
-
Removal of the old backstop near the playground
-
Repaint playground games
-
Miscellaneous site improvements around the school
April 2024
February 2024
September 2023
December 2023
July 2023
May 2023
COMMUNITY ENGAGEMENT PROCESS
Community Engagement
To ensure the school community is engaged in the project, the project manager (PM) will work directly with the school principal to discuss the identified renovations, meet with the architect, and coordinate the construction schedule. The principal will decide which school staff or parents might need to be involved with the design process depending on the scope of work. The project manager will share information with the entire school staff at key milestones through the design process.
SCOPE OF WORK
BUILDING ENVELOPE
- Repair exterior masonry
BUILDING SYSTEMS
- Repair/replace deteriorating electrical and plumbing system components to avoid potential system failure
INFRASTRUCTURE/SITE
-
Repair/replace chain link fence
-
Replace sports field equipment
-
Repair grass turf and irrigation system
-
Repair/replace concrete and paving
SAFETY/CODE
-
Install safety railings
-
Address building code fire safety issues
INTERIOR SPACE IMPROVEMENT
- Improve interior finishes such as wall coverings and paint