Monarch High
329 Campus Drive Louisville, CO 80027 | 720.561.4200
Original Construction Date | 1998
PHASE
Phase 2
PROJECT BUDGET
$15,370,576*
*Final budget will be determined during the design phase.
View Project Expenditures
CTE RENOVATIONS
The project budget includes $2.86M for renovations to create learning environments that support career & technical education.
PROJECT TEAM
PROJECT MANAGER: Charles Zachemsky
ARCHITECT: RTA Architects
CONTRACTOR: GH Phipps Construction
ARCHITECT: RTA Architects
CONTRACTOR: GH Phipps Construction
UPDATES
March 2025
Our $15.3 million renovation project will kick off this month. The improvements coming to our school are the result of the support from the entire BVSD community through passage of the 2022 BVSD Bond Referendum.
In addition to much needed repairs and upgrades to building systems and finishes, the project will include improvements to athletic facilities, auditorium upgrades, new flooring in most areas and significant renovations to our career and technical education spaces. Check out the highlights below for more details:
- Replace overhead doors in each academic wing with double swinging doors
- Replace synthetic turf and resurface track and tennis courts
- Auditorium improvements, including:
- New carpet
- Seating repairs
- New rigging and stage lighting
- Sound system upgrades
- Renovations to support Career & Technical education:
- Expanding the Training room and providing new equipment to support a new Exercise Science program;
- Opening up the Applied Tech room to create more space and flexibility; new flooring and paint;
- Expanding the lab and demonstration area in the Culinary classroom;
- Expanding the recording and broadcasting area and enhancing the space with new flooring, lighting, paint;
- Reconfiguring the Computer Science and Digital Arts spaces to increase flexibility
Previous Updates
DESIGN ADVISORY TEAM
Design Advisory Team
The Design Advisory Team (DAT) team includes teachers, staff, parents and community members who will work with the architects to develop the design for the project.
Members
John Cihlar, Teacher
Katherine Croasdale, Media Specialist
Greg Doan, Principal
Alex Esposito, Teacher
Autumn Francis, Teacher
Stephanie Gathright, Student
Linda Hubbard, Assistant Principal
Ghost Whitehall-Jacoby, Student
Laurel Jolly, Parent
Kate Klotz, Teacher
Kent Rieder, Parent
Mary Anne Scott, Parent
Katy Wood, Special Ed Teacher
Meeting Schedule
January 31, 2024 4:00pm - 5:30pm
MINUTES | PRESENTATION
February 21, 2024 4:00pm - 5:30pm
MINUTES | PRESENTATION
April 3, 2024 4:00pm - 5:30pm
MINUTES | PRESENTATION
May 1, 2024 4:00pm - 5:30pm
SUMMARY
SCOPE OF WORK
BUILDING ENVELOPE
- Repair/replace deteriorating areas of roof and roof components
-
Apply water repellent sealant to exterior masonry
-
Repair exterior stairs
BUILDING SYSTEMS
-
Repair/replace deteriorating HVAC, electrical and plumbing systems components to avoid potential systems failures
-
Replace exit signs
-
Replace kitchen dishwasher
-
Update lighting and lighting controls
-
Update obsolete HVAC controls
INFRASTRUCTURE/SITE
-
Repair/replace irrigation system components
-
Repair/replace concrete and asphalt paving
-
Replace synthetic turf field
-
Resurface tennis courts
-
Replace track surface
SAFETY/CODE
-
Address various ADA issues
-
Update fire protection system
INTERIOR SPACE IMPROVEMENT
-
Auditorium improvements
-
Improvements to interior finishes such as paint and flooring
-
Replace overhead doors
CAREER & TECHNICAL EDUCATION IMPROVEMENTS
The project budget includes $2.86M to invest in renovations to create learning environments to support career & technical education.