Monarch High
329 Campus Drive Louisville, CO 80027 | 720.561.4200
Original Construction Date | 1998
PHASE
Phase 2
PROJECT BUDGET
$15,370,576*
*Final budget will be determined during the design phase.
View Project Expenditures
CTE RENOVATIONS
The project budget includes $2.86M for renovations to create learning environments that support career & technical education.
PROJECT TEAM
PROJECT MANAGER: Charles Zachemsky
ARCHITECT: RTA Architects
CONTRACTOR: GH Phipps Construction
ARCHITECT: RTA Architects
CONTRACTOR: GH Phipps Construction

Check out the exciting new campus improvements at MHS!
UPDATES
July 2026
Welcome to the July Construction Update for Monarch High School! We hope summer is in full swing for you and your family, as it certainly is from our side of the fence, with plenty of work ahead from now to August. With a good portion of the summer behind us, we are pleased to report that the Monarch HS project is rolling along smoothly as we work toward substantial completion on Aug. 1 in time to welcome staff and students back to the building. Construction activity planned for the month of July is detailed below:
- Complete restroom(s) remodel on second floor, C wing
- Complete renovation of the student center
- Complete remodel of the business program
- Continue work on airflow issue in the C wing of the school
- Complete installation of carpet and paint in select areas of the C wing
- Complete installation of new lift station behind the kitchen
- Complete installation of stairway from the press box to the track/field
There are exciting changes coming to Monarch and we sincerely appreciate your patience as we work through the end of this summer project. Note that the school, and parts of the grounds, are still an active construction site. Thus, for the safety of everyone, we ask that you avoid coming to the campus unless absolutely necessary. The Boulder Valley School District is extremely grateful for the support given to us by the voters, and we strive to be good stewards in providing the best academic environments possible to support our students. Go Coyotes!
Previous Updates
- June 2026
- May 2026
- January 2026
- September 2025
- August 2025
- July 2025
- June 2025
- March 2025
- February 2025
- January 2025
- November 2024
- September 2024
- July 2024
- April 2024
- February 2024
- January 2024
- November 2023
- September 2023
- January 2023
June 2026
June 2026
Welcome to the June Construction Update for Monarch High School! With school officially over for the year and students and staff off for a well-earned summer break, the second summer of construction at Monarch HS is well underway. To allow the contractor to make the most of the summer “down time” the school building, along with select spots around the campus, are off limits to anyone besides construction personnel. This will be the case for the duration of the summer. Note: Campus Drive will be officially closed east of the Monarch K-8 entrance around mid June, with no public access for the duration of the summer. Students/staff needing to go to the Monarch HS campus will need to park at Monarch K-8 and walk over to the high school campus. With the exception of summer sports activities which are taking place on the campus as usual, we ask that you and your students avoid coming to the Monarch HS site unless specifically authorized to do so.
Below is an overview of the construction activities that will be taking place throughout the Monarch HS campus during the month of June:
- Begin demo at C-wing restrooms and begin remodel by end of June
- Begin demo at Student Center
- Fire/sprinkler improvements in select areas of the school
- Begin work on C-wing airflow issues, demo of existing system
- Begin installation of concrete stairs from the press box to the track/field
We are very excited about the changes in store for Monarch HS and sincerely appreciate your patience and support as we work our way through this final summer of construction. We hope you are having a wonderful and relaxing start to your summer break…Go Coyotes!
May 2026
May 2026
We hope the school year finished well for you and your student(s)! The BVSD Bond team is excited to let you know construction will resume this summer for the second construction season in our $15.3M renovation project provided through the Building for Student Success program. These improvements are coming to Monarch High School thanks to support from the entire BVSD community through passage of the 2022 Bond measure.
Highlights of the improvements coming this summer include:
- Renovations to support the expansion of Career and Technical Education opportunities
- HVAC improvements in C-wing
- Upper C-wing restroom conversion to single user all-gender stalls
- Replacement of PA/intercom system
- Renovation of Student Center
- Auditorium audio/video improvements
- Fire sprinkler system updates
- Additional bicycle parking
- Adding stairs from press box down to the track & field
The full scope of work can be found on the BVSD Building for Student Success website at bond.bvsd.org/school-projects/monarch-high-school.
Construction will begin after the students leave in May and will be complete when school resumes in August.
Student and staff safety is our top priority at Monarch High School and in the Boulder Valley School District. During the summer months, there will be very limited access to the building and school grounds. School administration and affected coaches and teachers have been notified of protocols to be followed for the limited access. For any questions regarding access, please reach out to the staff member in charge of the activity. For everyone’s safety, please comply with all posted signage and temporary barriers.
All workers who are authorized to be on-site will have numbered project stickers on their hard hats and will have background checks. Generally, there should be no reason for workers to interact with school staff or community members during this project.
We want to keep you informed as the project progresses. We will meet weekly with the architect(s) and construction company and will update you regularly about construction progress. Project information, including monthly construction updates can be found on the Monarch High School project website. Specific questions should be directed to me, Charles Zachemsky, at 720-561-5954 or charles.zachemsky@bvsd.org.
As always, we are extremely grateful to BVSD taxpayers for this project and to you for your continued support of Monarch High School. We hope you share our excitement for the great changes happening here.
Sincerely,
Charles Zachemsky
BVSD Project Manager
January 2026
September 2025
September 2025
Welcome to the September Construction Update for Monarch High School! Construction is substantially complete for the first year of the 2-year project. Students and staff are enjoying their new and renovated spaces and updates to our facilities outlined in the Critical Needs Plan! Final task-list items are being addressed and completed throughout the school but there should be no disruptions to the normal operations of the school. The track has been recently completed and all activities on this and the turf field have resumed. We appreciate everyone’s patience and flexibility while these were wrapped up.
Note that while some minor items will be completed throughout the school year, we will have another full summer of renovations in 2026 to complete this project. We hope you have a wonderful 2025-26 school year and look for more Bond Construction communication from BVSD beginning in May of 2026. Go Coyotes!
August 2025
August 2025
Welcome to the August Construction Update for Monarch High School! We are extremely excited to report that the summer 2025 Bond construction project is now substantially complete. Though we are just completing the first of a two year project, we are so appreciative of the staff, students and Monarch community for their patience and flexibility during this disruptive time on the MHS campus. As a reminder, here are some of the major items that were completed over the summer here at Monarch High School:
- New fire alarm system installed
- New athletic training room between the athletic locker rooms in the lower level
- New restrooms for students on the first floor classroom wing
- New turf field with customized endzone logos and rebuilt track*
- Resurfaced and repainted tennis courts
- Repaved and striped parking lot
- Remodeled career and technical education spaces
*Work on the surface of the track is ongoing due to unforeseen subgrade issues discovered in the course of construction. To allow the contractor to expedite the completion of this work, soccer and football practices and games have been relocated to other locations on the Monarch campus or other schools temporarily. Coaches will communicate details directly to athletes. In addition, the grass on the flag football field needs some additional time to fill in before it can be used. In the meantime, practices and games will be played on the Monarch PK-8 field. We are grateful for the flexibility and understanding of Monarch leadership, coaches, and athletes while we wrap up this part of the project.
July 2025
July 2025
Welcome to the July Construction Update for Monarch High School! We have passed the halfway point for the summer construction project. Plenty of work has been completed, with more to come. Construction crews are well on their way to being ready for students to return in August. Work to be completed this month is outlined below:
- Complete resurfacing/lining of the tennis courts and installation of new turf at the football field
- Complete installation of curb at the track, layout and installation of asphalt on the track
- Complete paving of visitor parking lot and new stairway entrance to gym area
- Ongoing roof work in select areas
- Complete all work in the new locker rooms, lower level, begin pre-punch in this area
- Ongoing fire alarm installation throughout the school
- Install new bleachers in the gym area
- Complete all electrical and overhead door work at the Coyote Cafe
- Complete installation of new restrooms on the first floor, begin addressing final tasks
- Complete paint and flooring in the administrative suite area
- Complete all work, including ceilings and casework, in CTE areas
June 2025
June 2025
Welcome to the June Construction Update for Monarch High School! With school officially over for the year and students and staff off for a well-earned summer break, construction at Monarch HS has ramped up immediately. As a reminder, the MHS Bond project is a complex and logistically challenging two-summer undertaking. We ask that you or your student(s) not come to the MHS campus unless specifically requested by a coach/sponsor or administrator. Note that the Monarch PK-8 small gym has now temporarily been converted into the MHS weight room with the MHS equipment now fully relocated there. All students who are instructed to meet for workouts with their coach/sponsor will go to the exit/entry door on the east side of the PK-8 to access this gym.
Below is an overview of the construction activities that will be taking place throughout the MHS campus during the month of June:
- Demo and complete resurfacing at the tennis courts
- Demo turf and begin to layout of the new turf at the football field
- Demo the track, complete prep work (subgrade) and begin to resurface the track by the end of June
- Demo stairway at gym, dock area, front entrance and visitor parking lot and begin pour-back and finishing of these areas
- Remove membrane from the roof and begin its replacement by the end of the month
- Begin and complete remodel of Coyote Cafe space (including overhead doors)
- Remove old generator and replace with new unit
- Demo lighting, ceiling grid and flooring and begin replacement in select classroom/commons areas
- Begin build-back of boys locker room area
- Begin school-wide fire alarm upgrades - ongoing
- Begin, and in some locations complete, build back of select classrooms and administrative area including lighting upgrades, ceiling, flooring and painting in select areas
March 2025
March 2025
Our $15.3 million renovation project will kick off this month. The improvements coming to our school are the result of the support from the entire BVSD community through passage of the 2022 BVSD Bond Referendum.
In addition to much needed repairs and upgrades to building systems and finishes, the project will include improvements to athletic facilities, auditorium upgrades, new flooring in most areas and significant renovations to our career and technical education spaces. Check out the highlights below for more details:
- Replace overhead doors in each academic wing with double swinging doors
- Replace synthetic turf and resurface track and tennis courts
- Auditorium improvements, including:
- New carpet
- Seating repairs
- New rigging and stage lighting
- Sound system upgrades
- Renovations to support Career & Technical education:
- Expanding the Training room and providing new equipment to support a new Exercise Science program;
- Opening up the Applied Tech room to create more space and flexibility; new flooring and paint;
- Expanding the lab and demonstration area in the Culinary classroom;
- Expanding the recording and broadcasting area and enhancing the space with new flooring, lighting, paint;
- Reconfiguring the Computer Science and Digital Arts spaces to increase flexibility
February 2025
January 2025
November 2024
September 2024
July 2024
April 2024
February 2024
January 2024
November 2023
September 2023
January 2023
DESIGN ADVISORY TEAM
Design Advisory Team
The Design Advisory Team (DAT) team includes teachers, staff, parents and community members who will work with the architects to develop the design for the project.
Members
John Cihlar, Teacher
Katherine Croasdale, Media Specialist
Greg Doan, Principal
Alex Esposito, Teacher
Autumn Francis, Teacher
Stephanie Gathright, Student
Linda Hubbard, Assistant Principal
Ghost Whitehall-Jacoby, Student
Laurel Jolly, Parent
Kate Klotz, Teacher
Kent Rieder, Parent
Mary Anne Scott, Parent
Katy Wood, Special Ed Teacher
Meeting Schedule
January 31, 2024 4:00pm - 5:30pm
MINUTES | PRESENTATION
February 21, 2024 4:00pm - 5:30pm
MINUTES | PRESENTATION
April 3, 2024 4:00pm - 5:30pm
MINUTES | PRESENTATION
May 1, 2024 4:00pm - 5:30pm
SUMMARY
SCOPE OF WORK
BUILDING ENVELOPE
- Repair/replace deteriorating areas of roof and roof components
-
Apply water repellent sealant to exterior masonry
-
Repair exterior stairs
BUILDING SYSTEMS
-
Repair/replace deteriorating HVAC, electrical and plumbing systems components to avoid potential systems failures
-
Replace exit signs
-
Replace kitchen dishwasher
-
Update lighting and lighting controls
-
Update obsolete HVAC controls
INFRASTRUCTURE/SITE
-
Repair/replace irrigation system components
-
Repair/replace concrete and asphalt paving
-
Replace synthetic turf field
-
Resurface tennis courts
-
Replace track surface
SAFETY/CODE
-
Address various ADA issues
-
Update fire protection system
INTERIOR SPACE IMPROVEMENT
-
Auditorium improvements
-
Improvements to interior finishes such as paint and flooring
-
Replace overhead doors
CAREER & TECHNICAL EDUCATION IMPROVEMENTS
The project budget includes $2.86M to invest in renovations to create learning environments to support career & technical education.
PROJECT PHOTOS