
Manhattan Middle School
290 Manhattan Drive Boulder, CO 80303 | 720.561.6300
Original Construction Date | 1965
PHASE
Phase 3
PROJECT BUDGET
$3,875,476*
*Final budget will be determined during the design phase.
View Project Expenditures
CTE RENOVATIONS
The project budget includes $455,000 for renovations to create learning environments that support career & technical education.
PROJECT TEAM
PROJECT MANAGER: Stephen Henry
ARCHITECT: Eidos Architects
CONTRACTOR: Swinerton
ARCHITECT: Eidos Architects
CONTRACTOR: Swinerton

UPDATES
August 2026
Welcome to the August Construction Update for Manhattan Middle School! As we wrap up the final odds/ends of the summer Bond Project here at Manhattan, we hope that you are as excited with the changes as we are. A great deal of work took place over a very short period of time (approximately 10 weeks), and like all summer projects, required complex coordination and cooperation between many entities. Below are a few of the tasks being completed (or have been completed) as your students return to school here in August:
- CTE area complete and new furniture and equipment installed
- ADA ramp completed at front entry
- Parking lot seal coated and restripped
- New flooring and ceiling tiles installed throughout the school
- New lighting completed and installed
- Punch list items being addressed throughout the site
As always, we cannot thank you enough for all of your patience during this past summer here at Manhattan MS. The 2022 BVSD Bond Project would not be possible without your generosity and we are grateful to be a part of a community that always steps up to support our students and the facilities that enhance their educational experience. We hope you and your student(s) have a wonderful start to the 2026 - 27 school year!
Previous Updates
- July 2026
- June 2026
- May 2026
- April 2026
- January 2026
- September 2025
- April 2025
- February 2025
- January 2025
- November 2024
- September 2024
- December 2023
- January 2023
July 2026
July 2026
Welcome to the July Construction Update for Manhattan Middle School! We hope summer is in full swing for you and your family, as it certainly is from our side of the fence, with plenty of work ahead from now to August. With a good portion of the summer behind us, we are pleased to report that the Manhattan project is rolling along smoothly as we work toward substantial completion on Aug. 1 in time to welcome staff and students back to the building. Construction activity planned for the month of July is detailed below:
- Complete fire alarm and intercom upgrade
- Complete lighting and ceiling grid replacement
- Complete flooring and furniture in new CTE classroom
- Complete flooring in select corridors, auditorium and choir room
- Complete ADA ramp installation and re-sealing of parking lot
- Complete repairs to underground water lines in select areas of the school
- Complete re-sealing of all windows
There are exciting changes coming to Manhattan MS, and we sincerely appreciate your patience as we work through the end of this summer project. Note that the school, and parts of the grounds, are still an active construction site. Thus, for the safety of everyone, we ask that you avoid coming to the campus unless absolutely necessary. The Boulder Valley School District is extremely grateful for the support given to us by the voters, and we strive to be good stewards in providing the best academic environments possible to support our students. Go Phoenixes!
June 2026
June 2026
Welcome to the June Construction Update for Manhattan Middle School! With school officially over for the year and students and staff off for a well-earned summer break, construction at Manhattan MS is well underway. To allow the contractor to make the most of the summer “down time” the school building, along with select spots around the campus, are off limits to anyone besides construction personnel. This will be the case for the duration of the summer. Below is an overview of the construction activities that will be taking place throughout the Manhattan campus during the month of June:
- Demo of most bathrooms begins along with the current CTE space on the west side
- Select abatement activity will be completed in June
- Begin/complete demolition of ceiling tile, grid in the corridors
- Begin floor preparation for new flooring
- Demo and begin replacing lights with new LED fixtures
- Begin work on new fire alarm controls and PA system replacement
- Begin resurfacing of main parking lot and ADA access
While the majority of the surrounding campus is accessible to the public, we ask that you and your students avoid coming to the school building itself unless specifically authorized to do so. We are very excited about the changes in store for Manhattan and sincerely appreciate your patience and support as we work our way through this busy summer of construction. We hope you are having a wonderful and relaxing start to your summer break!
May 2026
May 2026
Dear Manhattan Middle School Parents and Staff,
We hope this has been a successful school year for you and your student(s)! The BVSD Bond team is excited to let you know construction will be starting soon for renovations provided by the Building for Student Success program. These improvements are coming to Manhattan Middle School thanks to support from the entire BVSD community through passage of the 2022 Bond measure.
In addition to much-needed repair and upgrades to building systems and finishes, highlights of the improvements coming to Manhattan Middle include:
- Concrete repair and replacement
- Scoreboard replacement
- Improvements to interior finishes such as flooring and painting
- Renovations to select restrooms
- Renovations to expand opportunities for career and technical education
The full scope of work can be found on the BVSD Building for Student Success website on the Manhattan Middle School project page.
Our $3.7 million project will begin after the students leave in May and is scheduled to be completed by the time students return in August. There will be no public access to the school or grounds over the summer.
Student and staff safety is our top priority at Manhattan Middle School and in the Boulder Valley School District. All workers who are authorized to be on-site will have numbered project stickers on their hard hats and will have background checks. There should be no reason for workers to interact with students or staff while they are in the school.
We want to keep you informed as the project progresses. We will meet weekly with the architect(s) and construction company and will update you regularly about construction progress during the summer months. Project information, including monthly construction updates can be found on the Manhattan Middle School project website. Specific questions should be directed to me, Stephen Henry at 720-561-5953 or stephen.henry@bvsd.org.
As always, we are extremely grateful to BVSD taxpayers for this project and to you for your continued support of Manhattan Middle School. We hope you share our excitement for the great changes happening here.
Sincerely,
Stephen Henry
BVSD Project Manager
-------------------------------------------------------------------------------------------------
May 2026
Project postcards were sent to neighbors this month.

April 2026
January 2026
September 2025
September 2025
The project teams are in the final stages of design for the Phase 3 projects. Construction documents will be issued in the fall and the contractor’s guaranteed maximum price (GMP) will go to the Board for approval in November. Construction is expected to kick off in May 2026 after the students leave for summer break.
April 2025
February 2025
January 2025
November 2024
September 2024
December 2023
January 2023
DESIGN ADVISORY TEAM
Design Advisory Team
The Design Advisory Team (DAT) team includes teachers, staff, parents and community members who will work with the architects to develop the design for the project.
Members
Melanie Crowder, Teacher
Brent Graham, Assistant Principal
Adam Hunt, Teacher
Kristen Lewis, Principal
Alaina McQueen, Teacher
Brooke Smith, Teacher
Holly Williams, Parent
Meeting Schedule
January 29, 2025
Minutes
SCOPE OF WORK
BUILDING SYSTEMS
- Repair/replace deteriorating plumbing system components to avoid potential systems failures
-
Replace scoreboard
INFRASTRUCTURE/SITE
- Repair/replace concrete where needed
SAFETY/CODE
- Address various ADA issues
INTERIOR SPACE IMPROVEMENT
-
Improvements to interior finishes such as painting and flooring
-
Replace student lockers
-
Renovate select student restrooms
CAREER & TECHNICAL EDUCATION IMPROVEMENTS
The project budget includes $455,000 to invest in renovations to create learning environments to support career & technical education.

