Justice High School
805 Excalibur Lafayette, CO 80026 | 720.277.6480
Original Construction Date | 1979
Phase 1
PROJECT BUDGET
$719,155*
*Final budget will be determined during the design phase.
View Project Expenditures
PROJECT TEAM
PROJECT MANAGER: Stephen Henry
ARCHITECT: Wold
CONTRACTOR: Alliance Construction Solutions
UPDATES
August 2024
​Thanks to your tax dollars big changes happened here in 2024!
The Critical Needs work has been completed and this will conclude our updates. This and other construction work around the Boulder Valley School District could not be possible without the generous support from our voters and the entire BVSD community. We are extremely grateful for this support and are thrilled for the Justice High School community and its students!
Previous Updates
- July 2024
- June 2024
- May 2024
- March 2024
- February 2024
- December 2023
- September 2023
- July 2023
- May 2023
July 2024
June 2024
May 2024
May 2024
Students and staff are enjoying the building improvements and renovated athletic field! The field will be closed until the end of the month to allow the new sod to take root. A roofing contractor will be on-site this month to replace the shingle rooftop. All work is anticipated to be completed by the first week of June.
March 2024
March 2024
Welcome the first of several communications regarding the upcoming construction project at Justice High School! Thanks to the generous support of community members like yourself via the 2022 Bond, BVSD is able to bring improvements to select areas of the school site that will improve access for activities as well as improving the overall quality of the learning environment. Mobilization for this work begins Monday, Mar. 25 during Spring Break with substantial completion slated for late April. Here are some of the highlights of this exciting 2-month project:
- Removal of far east parking lot and vehicles currently stored there
- Installation of new grass field on the east side of the Justice HS property
- Removal of the chimney in front of the school and replacing with an improved facade
- Improvements to ADA access at select areas around the school
- Site improvements such as sidewalk improvements and other landscaping
February 2024
December 2023
September 2023
July 2023
May 2023
COMMUNITY ENGAGEMENT PROCESS
Community Engagement
To ensure the school community is engaged in the project, the project manager (PM) will work directly with the school principal to discuss the identified renovations, meet with the architect, and coordinate the construction schedule. The principal will decide which school staff or parents might need to be involved with the design process depending on the scope of work. The project manager will share information with the entire school staff at key milestones through the design process.
SCOPE OF WORK