Horizons K-8 School
4545 Sioux Drive Boulder, CO 80303 | 720.561.3600
Original Construction Date | 1959
PHASE
Phase 2
PROJECT BUDGET
$1,496,816*
*Final budget will be determined during the design phase.
View Project Expenditures
PROJECT TEAM
ROJECT MANAGER: Matt Johnson
ARCHITECT: Eidos Architects
CONTRACTOR: Taylor Kohrs
ARCHITECT: Eidos Architects
CONTRACTOR: Taylor Kohrs

UPDATES
September 2025
Construction is substantially complete and the project team is working with the contractor to finish final task list items and close out the project. Students and staff are enjoying the updated spaces and improvements! This and other construction work around BVSD could not be possible without the generous support from our voters and the entire BVSD community. We are extremely grateful for this support and are thrilled for the Horizons K8 community and its students!
Previous Updates
- August 2025
- July 2025
- June 2025
- May 2025
- April 2025
- February 2025
- January 2025
- November 2024
- September 2024
- July 2024
- May 2024
- April 2024
- February 2024
- September 2023
- January 2023
August 2025
August 2025
Welcome to the August Construction Update for Horizons K-8 School! We are extremely excited to report that the summer 2025 Bond construction project is now substantially complete. While there are a few final items being addressed during the month of August, the bulk of the work is now completed and the school is up and running as usual. As a reminder, here are some of the major items that were completed over the summer here at Horizons K-8:
- Upgraded lighting to LED throughout the school
- Replaced water heater pumps
- Repaired/replaced pavement where needed
- Replaced irrigation system and turf grass - northwest side of the property
- Updated fire protection system
- Updated access control system
- Updated intercom system
- Added two new Special Education offices and remodeled instructional space
- Upgraded the roof top HVAC unit to service additional office space
- Installed an additional gender neutral restroom (main hallway)
Overall, the entire school site looks amazing, and we are thrilled about the work that has been completed. As always, this and other facility improvements around BVSD could not be possible without the support and generosity of the entire BVSD community and we sincerely thank you for your support. Have a great start to the 2025-26 school year!
July 2025
July 2025
Welcome to the July Construction Update for Horizons K-8 School! We have passed the halfway point for the construction project here at Horizons--plenty of work has been completed with more to come. Construction crews are well on their way to being ready for students to return in August. Work to be completed this month is outlined below:
- Complete asphalt overlay, crack seal, and striping of parking lot
- Complete installation of new fire alarm system
- Complete installation of new lights in select areas of the school
- Complete installation and testing of new hydronic heating and cooling system
- Complete installation of new bathroom accessories in main corridor
- Complete remodel of new Learning Lab space
- Begin addressing final task list items throughout the month when possible
- Begin prep for new roof top HVAC unit for Special Education space. Delivery of the roof top HVAC unit has been delayed. However, students and staff will still be able to use the renovated space when they return in August. Installation of the unit once delivered will happen outside of regular school hours.
We are very excited about the work that has been done so far at Horizons, and we believe you will be too! As always, we thank you for your support in making this project possible.
June 2025
June 2025
Welcome to the June Construction Update for Horizons K-8 School! With school officially over for the year and the students and staff off for a well-earned summer break, construction at Horizons is well underway. As such, the school building, along with select spots around the campus, are currently off limits to anyone besides construction related personnel. However, most of the surrounding grounds and playgrounds are all accessible to the public. For the safety of everyone, we do ask that you adhere to all fencing and signage instructions as work continues over the duration of the summer. Below is an overview of the construction activities that will be taking place throughout the Horizons campus during the month of June:
- Playing field turf maintenance, including top dressing, aeration and seeding
- Demolition of the existing fire alarm system to begin replacement by the end of June
- Begin replacement of lighting upgrades in select areas of the school - ongoing all summer
- Replacement of hydronic to better serve the existing boilers
- Remodel new bathroom at main corridor
- Begin demo and build out of new Special Education space, including office and learning spaces
May 2025
May 2025
We hope this message finds you and your student(s) well as we quickly approach the end of the school year! The BVSD Bond Department is excited for the upcoming kick-off of construction for renovations coming to Horizons K8 this summer. The improvements are the result of the support from the entire BVSD community through passage of the 2022 BVSD Bond Referendum.
Our $1.5M project will begin immediately after Memorial Day weekend (with some site mobilization taking place in the days leading up to the end of school) and will be substantially complete by early August. Highlights of the project include:
- Upgrade lighting to LED
- Replace water heater
- Repair/Replace pavement where needed
- Replace irrigation system and turf grass
- Update fire protection system
- Update access control system
- Update intercom system
- Add two new Special Education offices
- Upgrade RTU to service additional office space
- Install additional gender neutral restroom
April 2025
February 2025
January 2025
November 2024
September 2024
July 2024
May 2024
April 2024
February 2024
September 2023
January 2023
COMMUNITY ENGAGEMENT PROCESS
Community Engagement
To ensure the school community is engaged in the project, the project manager (PM) will work directly with the school principal to discuss the identified renovations, meet with the architect, and coordinate the construction schedule. The principal will decide which school staff or parents might need to be involved with the design process depending on the scope of work. The project manager will share information with the entire school staff at key milestones through the design process.
SCOPE OF WORK
BUILDING ENVELOPE
- Repair/replace deteriorating areas of roof and roof components
BUILDING SYSTEMS
-
Upgrade deteriorated lighting to LED
-
Replace water heater
INFRASTRUCTURE/SITE
-
Repair/replace pavement where needed
-
Repair irrigation system and turf grass
SAFETY/CODE
-
Update fire protection system
-
Update access control system
-
Update intercom system
INTERIOR SPACE IMPROVEMENT
- Improve interior finishes such as ceiling tile