Centennial Middle School
2205 Norwood Avenue Boulder, CO 80304 | 720.561.5441
Original Construction Date | 1960
PHASE
Phase 3
The tennis courts were reconstructed in 2024. The remainder of the project will be completed in Phase 3.
PROJECT BUDGET
$6,007,500*
*Final budget will be determined during the design phase.
View Project Expenditures
CTE RENOVATIONS
The project budget includes $455,000 for renovations to create learning environments that support career & technical education.
PROJECT TEAM
PROJECT MANAGER: Gene Temanson
ARCHITECT: Eidos Architects
CONTRACTOR: Palace Construction

UPDATES
July 2026
Welcome to the July Construction Update for Centennial Middle School! We hope summer is in full swing for you and your family, as it certainly is from our side of the fence, with plenty of work ahead from now to August. With a good portion of the summer behind us, we are pleased to report that the Centennial project is rolling along smoothly as we work toward substantial completion on Aug. 1 in time to welcome staff and students back to the building. Construction activity planned for the month of July is detailed below:
- Complete remodel of CTE area on second floor (former computer lab)
- Complete ceiling and LED light replacement in select areas of the school
- Complete upgrade of staff and student restrooms by the faculty lounge
- Complete finishes in lower gym, including floor, paint and other detailing
- Complete parking lot striping
There are exciting changes coming to CMS, and we sincerely appreciate your patience as we work through the end of this summer project. Note that the school, and parts of the grounds, are still an active construction site. Thus, for the safety of everyone, we ask that you avoid coming to the campus unless absolutely necessary.
The Boulder Valley School District is extremely grateful for the support given to us by the voters, and we strive to be good stewards in providing the best academic environments possible to support our students. Go Cyclones!
Previous Updates
- June 2026
- May 2026
- April 2026
- January 2026
- September 2025
- April 2025
- February 2025
- January 2025
- November 2024
- September 2024
- June 2024
- December 2023
- January 2023
June 2026
June 2026
Welcome to the June Construction Update for Centennial Middle School! With school officially over for the year and students and staff off for a well-earned summer break, construction at Centennial MS is well underway. To allow the contractor to make the most of the summer “down time” the school building, along with select spots around the campus, are closed to anyone besides construction personnel. This will be the case for the duration of the summer. Below is an overview of the construction activities that will be taking place throughout the CMS campus during the month of June:
- Abatement activities in the lower gym (specifically floor tile removal and replacement)
- Begin demo in the computer lab (CTE area)
- Complete demo, and begin reinstallation, of corridor ceiling grid and tile, primarily in the first floor area
- Begin rough-in for new LED lighting and new intercom system
- Begin demolition of staff restroom and student restrooms by the staff lounge
While the majority of the surrounding campus is accessible to the public, we ask that you and your students avoid coming to the school building itself unless specifically authorized to do so. We are very excited about the changes in store for CMS and sincerely appreciate your patience and support as we work our way through this busy summer of construction. Have a wonderful and relaxing summer break
May 2026
May 2026
Dear Centennial Middle School Parents and Staff,
We hope this has been a successful school year for you and your student(s)! The BVSD Bond team is excited to let you know construction will be starting soon for renovations provided by the Building for Student Success program. These improvements are coming to Centennial Middle School thanks to support from the entire BVSD community through passage of the 2022 Bond measure.
In addition to much-needed repair and upgrades to building systems and finishes, highlights of the improvements coming to Centennial Middle include:
- Concrete and paving repair and replacement
- Roof repair and replacement
- Improvements to interior finishes such as flooring, painting and ceilings
- Baseball/softball bleacher replacement
- Select restroom renovations
- Renovations to expand opportunities for career and technical education
The full scope of work can be found on the BVSD Building for Student Success website on the Centennial Middle School project page.
Our $6 million project will begin after the students leave in May and will be complete when school resumes in August.
Student and staff safety is our top priority at Centennial Middle School and in the Boulder Valley School District. During the summer months, there will be no access to the building and school grounds. For everyone’s safety, please comply with all posted signage and temporary barriers.
All workers who are authorized to be on-site will have numbered project stickers on their hard hats and will have background checks. Generally, there should be no reason for workers to interact with school staff or community members during this project.
We want to keep you informed as the project progresses. We will meet weekly with the architect(s) and construction company and will update you regularly about construction progress during the summer months. Project information, including monthly construction updates can be found on the Centennial Middle School project website. Specific questions should be directed to me, Gene Temanson at 720-561-5951 or gene.temanson@bvsd.org.
As always, we are extremely grateful to BVSD taxpayers for this project and to you for your continued support of Centennial Middle School. We hope you share our excitement for the great changes happening here.
Sincerely,
Gene Temanson
BVSD Project Manager
---------------------------------------------------------------------------------------
May 2026
Project postcards were sent to neighbors this month.

April 2026
January 2026
September 2025
September 2025
The project teams are in the final stages of design for the Phase 3 projects. Construction documents will be issued in the fall and the contractor’s guaranteed maximum price (GMP) will go to the Board for approval in November. Construction is expected to kick off in May 2026 after the students leave for summer break.
April 2025
February 2025
January 2025
November 2024
September 2024
June 2024
December 2023
January 2023
DESIGN ADVISORY TEAM
Design Advisory Team
The Design Advisory Team (DAT) team includes teachers, staff, parents and community members who will work with the architects to develop the design for the project.
Members
Members will be determined when the project begins.
Meeting Schedule
The meeting schedule will be determined when the project begins.
SCOPE OF WORK
BUILDING ENVELOPE
- Repair masonry joints and re-caulk control joints
-
Repair/replace deteriorating areas of roof and roof components
-
Replace select skylights
BUILDING SYSTEMS
- Replace deteriorating HVAC and plumbing systems components to avoid potential system failure
INFRASTRUCTURE/SITE
-
Repair/replace exterior concrete & pavement
-
Repair/replace tennis court surfacing (completed in 2024)
-
Replace tennis court fence (completed in 2024)
-
Replace baseball/softball bleachers
SAFETY/CODE
-
Address various ADA needs
-
Install safety railings and ladders
-
Update fire protection system
INTERIOR SPACE IMPROVEMENT
-
Interior finish improvements such as flooring, paint, and ceilings
-
Select restroom renovations
CAREER & TECHNICAL EDUCATION IMPROVEMENTS
The project budget includes $455,000 to invest in renovations to create learning environments to support career & technical education.