Apex, Arapahoe Ridge High School, Boulder Universal, and Transitions
6600 East Arapahoe Avenue Boulder, CO 80303 | 720.561.5258
Original Construction Date | 1963
PHASE
Phase 2
PROJECT BUDGET
$29,649,119
*Final budget will be determined during the design phase.
View Project Expenditures
CTE IMPROVEMENTS
$21.5M will be invested in renovations at Apex (formerly Boulder TEC) to modernize current spaces to transform them into more accurate industry environments that mimic what students will experience in the workforce.
PROJECT TEAM
PROJECT MANAGER: Charles Zachemsky
ARCHITECT: Cunningham Group
CONTRACTOR: FCI Constructors

UPDATES
January 2026
Welcome to the January Construction Update for the Arapahoe Campus! We hope this message finds you well and that you and your family had a wonderful holiday season. A lot of activity has taken place on the Arapahoe Campus during the past couple of weeks, both inside and outside of the school. This month, students and staff returned to a transformed main entrance, remodeled APEX administrative suite, and renovated classrooms on the first floor of the northeast wing which will house the Biomedical, Exercise Science, EMT, and Criminal Justice programs. Active construction has moved into the former Biomedical, EMT, Exercise Science, and Criminal Justice areas, as well as the former APEX administrative offices. These spaces will be remodeled to house Computer Science, Aerospace/Aviation, and Video Production. This next phase of construction will also include a new addition which will house a common area for students, as well as renovating the outdoor courtyard space. Construction will continue in these areas until May. The final phase of the project will include renovations to existing Construction Trades, Auto Collision and Welding spaces and new spaces for Quantum Manufacturing and Optical Engineering. The entire project is on schedule to be completed in the fall of 2026.
With the shift in location of active construction, circulation in the school has changed. Students will need to be attentive to and follow all pertinent construction signage and wayfinding instructions on campus.
Previous Updates
- October 2025
- September 2025
- August 2025
- July 2025
- June 2025
- May 2025
- April 2025
- March 2025
- February 2025
- November 2024
- September 2024
- July 2024
- April 2024
- March 2024
- January 2024
- November 2023
- September 2023
- January 2023
October 2025
October 2025
Welcome to the October Construction Update for the Arapahoe Campus! Phase III of the project is moving along smoothly and is well over half-way complete. Work inside the school during this phase is happening in the admin suite, main entry lobby, and the rooms across the corridor where spaces for BioMed, Physical Therapy/Sports Medicine, Medical Assisting and Pharmacy Tech will be created. Outside the school, the front entrance is getting a large-scale makeover.
Students and staff have adjusted to some rerouting on the site while this work continues, and we appreciate their patience and support as it certainly helps the project move along in a predictable and uninterrupted manner. Please be reminded that this project will be ongoing throughout the 2025-26 school year, and through the summer of 2026. Activity planned for the month of October is outlined below:
Interior Phase III
- Complete drywall installation throughout the spaces
- Prime and first coat of paint
- Install steel at main staircase
- Install ceiling grid and begin installation of ceiling tiles
- Mechanical, Electrical and Plumbing trim out
- New front entry storefront installation completed
Exterior Phase III
- Backfill foundation wall at remodeled exterior entrance
- Complete grade beams at exterior entrance
- Excavate for monument sign, install conduit to the site
- Install steel railings at the entrance
- Complete monument sign footer and wall
September 2025
September 2025
Welcome to the September Construction Update for the Arapahoe Campus! Phases I and II of this two year project are now substantially completed. Phase III is fully underway in the first floor areas of future APEX classrooms and offices. Note that this project will be ongoing throughout the 2025-26 school year, and through the summer of 2026, and that we will be continuing these monthly communications throughout the duration of the project. There is a substantial amount of activity happening both inside and outside of the campus currently. Please see below for specific details on the work taking place during the month of September:
Interior Phase III
- Complete all plumbing inspections in new office and classroom areas
- Complete installation of wall backing in all new classrooms
- Begin installation of drywall and rough finish in all classrooms and offices
- Infill steel and pourback at main stairs inside entrance
Exterior Phase III
- Install underground mechanical/electrical/plumbing at entrance
- Complete grading and installation of walls and pilasters
August 2025
August 2025
Welcome to the August Construction Update for the Arapahoe Campus! We are extremely excited to report that Phase 2 (of 5) of the 2022 Bond construction project is now substantially complete. Though we are just completing the first summer of a two year project, we are so appreciative of the staff, students and Arapahoe Campus community for their patience and flexibility during this disruptive time. Here are some of the exciting changes students will return to this month:
- New classrooms, offices and conference rooms for Arapahoe Ridge High School
- New interior and exterior windows to bring natural light to areas without it
- New counseling spaces for Apex students
- New classrooms for the Teacher Academy
- Newly renovated spaces for Boulder Universal
- New Criminal Justice, Behavioral Health, and Emergency Medical Technician areas have been completed, including an outdoor learning patio and will be available in January. (Access to the space is currently restricted due to other construction.)
With the substantial completion of these areas, crews have moved on to the next phase of the project which will include a major renovation to the front entry and Apex administration area as well as renovations to the first floor to create spaces for BioMed, Physical Therapy/Sports Medicine, Medical Assisting and Pharmacy Tech.
July 2025
July 2025
Welcome to the July Construction Update for the Arapahoe Campus! We have passed the halfway point for the first summer of construction--plenty of work has been completed, with more to come. Construction crews are well on their way to being ready for students to return in August. Work to be completed this month is outlined below:
- Complete courtyard landscaping and sod installation
- Complete final paint and hanging of doors in new Level 2 spaces
- Complete build-out of fire pump room and fire line install
- Final paint, carpet, and rail install at Boulder Universal room
- Complete all items in ARHS areas A & B, including final paint and begin to address final task list items
- Complete final tasks in new multi and single bathroom, ARHS area, Level 2
- Complete window in Level 2 corridor, ARHS area
- Complete framing, walls, overhead doors and landscaping at mechanical room
We are very excited about the work that has been done so far at the Arapahoe Campus, and we believe you will be too! As always, we thank you for your support in making this project possible. We hope you continue to have a wonderful summer vacation!
June 2025
June 2025
Welcome to the June Construction Update for the Arapahoe Campus! With school officially over for the year and the students and staff off for a well-earned summer break, construction at the Arapahoe Campus has ramped up considerably from the work being done in the past few months. As a reminder, this project kicked off in March and will be ongoing throughout the site up through August of 2026. Taking advantage of the summer “down time” at a school is of utmost importance in a multi-phased project like this and both BVSD and FCI Constructors have put in place a plan to ensure this time is maximized before students return to school in mid-August. As such, the entire building, along with most of the surrounding campus, is off limits to anyone besides construction related personnel as work is taking place at several locations throughout the campus.
Below is an overview of the construction activities that will be taking place during the month of June:
- Complete final clean and wrap up tasks on Level 1 and 2 of the Phase 1 work area (former child care location)
- Begin and complete courtyard improvements, including pouring of concrete & striping, ornamental fencing, irrigation repairs, landscape covering & boulder placement
- Complete all activities in new fire pump room and begin final build-out of this room
- Complete fire line installation to the above room
- Complete carpet tile installation at former IT area along with framing a drywall installation in a few select areas of this space
- Begin and complete work on second floor of ARHS Phase 2 area, new window openings to outside, select classroom demo, layout and bathroom remodel
- Complete installation of corridor windows at ARHS area 2, level 2
- Complete abatement at the former cosmetology area and begin demo and initial framing for remodel in select locations
May 2025
May 2025
Welcome to the May Construction Update for the Arapahoe Campus. The end of the 2024-25 school year is fast approaching, and we hope this message finds both you and your family well during this busy time of the school year!
On the construction front, work around the campus has continued through the early spring months (primarily in the Apex (formerly Boulder TEC) area of the campus) and the transition to full summer construction is underway. This coming summer’s construction activities will be extensive and the entire campus will be closed to all students and staff. As a reminder, in this multi-phase project, construction will continue in the building and around the campus throughout the 2025-26 school year. The active construction areas will move to different locations as the project progresses until it is completed in the fall 2026. We will provide monthly updates moving forward to keep you informed of the work happening and any impact it may have on the day-to-day operations of the campus and the various programs housed there.
Below is a brief description of the work planned for the month of May:
Apex Area, Phase I, First Floor
- Prime and paint in select areas
- Grind and polish floors throughout the area
- Install operable partitions, ceiling grid, exterior louvres and casework
- Install drop ceiling tiles
- Hang doors and install hardware
- Install teaching wall, audio enhancement and signage
April 2025
April 2025
The 2025 Bond Project has officially begun on phase 1 of our five-phase project. Our general contractor, FCI, has fully mobilized to the site and set up construction areas in several locations. An extensive amount of work was completed over spring break, including demolition to prepare for our updated spaces. Four Arapahoe Ridge High School classes have moved to temporary classrooms, and BVSD’s Information Technology department has moved out of the building. Limited construction activity will continue in specific areas noted below over the coming weeks before once again ramping up fully after school is out in May. Below is an overview on the work that is taking place in the month of April:
Phase 1, Level 1: Previous Child Care Area:
- Complete demolition of select walls, sawcut and layout of new walls/partitions
- Complete mechanical/electrical/plumbing (MEP), fire sprinkler and technology rough-in
- Complete installation of partition tracks and partitions
- Complete installation of framing, backing and drywall
- Complete prime and first coat of paint
- Complete ceiling grid and ceiling tile installation
- Complete grinding and polishing of floors
- Install all casework
- Complete MEP trim and all systems connections
- Begin installation of exterior louvers
Phase 1, Level 2: Media Center and surrounding rooms:
- Complete layout of new walls, partitions and framing
- Complete electrical, fire sprinkler and technology rough-in
- Complete installation of partition tracks and partitions
- Complete installation of backing and gyp board walls
- Complete prime and first coat of paint
- Complete ceiling grid and ceiling tile installation
- Complete grinding and polishing of floors
- Install all casework
- Complete security and lighting trim along with all systems connections
- Complete final paint
March 2025
March 2025
This month we will officially kick-off construction for our $29 million building renovation project! The improvements coming to our schools are thanks to the generous support of the entire BVSD community through passage of the 2022 BVSD Bond Referendum.
The project will address some critical facilities needs such as HVAC, electrical and plumbing upgrades, ADA needs, and installing a fire suppression system, as well as a kitchen expansion for the Transitions building. The majority of the project involves reconfiguring spaces throughout the main building to consolidate programs and expand learning spaces to create more opportunities for hands-on, career and college readiness learning. District office space on the northeast side of the building will be renovated to create learning spaces for Boulder Universal. Arapahoe Ridge High School will take over the east wing of the second floor, which will be updated with large windows, new flooring and paint and a new commons area. New space for the Teacher Academy will also be created on the second floor, along with a counseling center. The former Early Connections area of the first floor will be renovated to house the Emergency Medical and Criminal Justice programs. The front entry will get a makeover and a new area designed to host industry partners will be created near the administration suite.
February 2025
November 2024
September 2024
July 2024
July 2024
- Boulder TEC and having centralized CTE programs is the focus of this bond project. The design team is working to modernize our current spaces along with expanding programmatic opportunities. ARHS will also have some exciting updates including a design that will allow all of their programs to be in the same area of the building. Updated building systems including a fully sprinkled building is our critical needs focus.
- SD documents were issued April 12th with SD pricing returned from FCI within budget. The team is currently vetting out the design build process for the fire sprinkler throughout the building.
- DD package is scheduled to be issued July 15th, with final CDs scheduled to deliver to BVSD on October 11th.
April 2024
March 2024
March 2024
Exciting things are happening at our school building, and we want to tell you about what’s in store for the coming months.
Thanks to the generous voters of Boulder Valley School District (BVSD), we are beginning work on a $25M building renovation project on the building that houses Arapahoe Ridge High School, Boulder Universal, and Boulder TEC. With this project, Boulder TEC will be transformed into a centralized career acceleration center for the district. The renovation project also includes much-needed repairs and upgrades to building systems and finishes, such as updating HVAC, electrical and plumbing systems, installing a fire suppression system, and addressing various ADA needs. With this large-scale renovation, there will be some reconfiguration of rooms inside the building, with some learning spaces and administration areas relocating. The details of the design and specific floor plan will be developed through the design process.
The goal of the Boulder TEC renovation is to ensure all future offerings lead to high-demand, high wage career opportunities for students. The project will build upon Boulder TEC’s strengths, while improving the learning environment and expanding career exploration opportunities.
Boulder TEC’s administration and advisory committees have been evaluating the current programming, which includes biomedical science, automotive and collision repair, construction technology, criminal justice, emergency medical services, physical therapy, sports medicine, video production, and more. Changes are being explored to update and modernize BVSD’s offerings including the potential additions of environmental science and sustainability, health and medical, as well as quantum information science and technology. The updated facility will serve as a central hub for students who are ready to accelerate their academic careers by pursuing college credit, industry credentials and internships.
The project is currently in the early design stages. We have convened a design advisory team (DAT) of school staff, students, and parents to work with the project architect to guide the design for the renovations. Many decisions about the final design of the improvements will be determined through the discussions of the DAT. More information about the project, including the full scope of work and project updates can be found on the Boulder TEC/Arapahoe Ridge High/Boulder Universal project website.
We anticipate construction will begin spring/summer (2025). Closer to the start of construction, we will contact you with more information about what to expect. We are very excited about these changes and hope you will be too. Please direct questions about the project to Charles Zachemsky at charles.zachemsky@bvsd.org or 720-561-5954.
Sincerely,
Dr. Joan Bludorn, Arapahoe Ridge High Principal,
Dr. Arlie Huffman, Director of Career and College Connections
Eric Moroye, Boulder Universal Principal
January 2024
November 2023
September 2023
January 2023
January 2023
This month, the new CTE Steering Committee met for the first time. In the coming months the group will work with architects from DLR Group to develop a master plan to guide the district-wide CTE improvements funded in the 2022 capital improvement program. Moving forward, the group will work to identify and collect key data that will help inform this project, such as industry needs/future career openings, community & student interest and current CTE programming options. This work will build upon recommendations from the Career Discovery and Postsecondary Readiness Committee that concluded last spring. The goals of the committee were to explore programming opportunities and current barriers and propose next steps to expanding CTE in Boulder Valley School District.
DESIGN ADVISORY TEAM
Design Advisory Team
The Design Advisory Team (DAT) team includes teachers, staff, parents and community members who will work with the architects to develop the design for the project.
Members
Amy Buss, CTE Counselor
Ash Collins, Teacher
A. Ellis, Student
M. Johnson, Student
D. Licknosky, Student
Darrin Rasmussen, Teacher
Dan Rosseau, Teacher
Meeting Schedule
February 1, 2024 3:30pm - 5:00pm
MINUTES | PRESENTATION
February 29, 2024 3:30pm - 5:00pm
MINUTES | PRESENTATION
March 21, 2024 3:30pm - 5:00pm
MINUTES | PRESENTATION
April 25, 2024 3:30pm - 5:00pm
MINUTES | PRESENTATION
September 4, 2024 3:30pm - 5:00pm
SCOPE OF WORK
BUILDING SYSTEMS
-
Replace deteriorating HVAC, electrical, & plumbing systems components to avoid potential system failure
-
Update obsolete HVAC controls
SAFETY/CODE
-
Address various ADA needs
-
Install fire suppression system
INTERIOR SPACE IMPROVEMENT
-
Interior finish improvements such as flooring, paint, and ceilings
-
Renovate select restrooms to be ADA compliant
CAREER & TECHNICAL EDUCATION IMPROVEMENTS
Apex (formerly Boulder TEC) has large industry-inspired learning labs where 11th and 12th-grade students can earn college credits and career-enhancing certifications while maintaining home high school enrollment. Renovations proposed for Apex will modernize current spaces to transform them into more accurate industry environments that mimic what students will experience in universities and work environments.
These renovations will build a stronger bridge between education and the worlds of college and work so that our students are ready and nimble to make the transition from learner to producer. By revolutionizing these spaces, BVSD students will have the optimum environments to gain real-world, hands-on experiences in in-demand fields such as Cybersecurity, Biomedical Science, Creative Media Production, Computer Science, Engineering, Healthcare, Culinary Arts, and more.
PROJECT PHOTOS
Building for Student Success & CTE Update to Board
Oct. 24, 2023
Bond investment leads to cutting-edge career acceleration at BVSD
Career and Technical Education (CTE), now known as ‘Accelerate’ in the Boulder Valley School District (BVSD), is a core component of BVSD’s secondary curriculum and the BVSD Grad Plus framework, which expands graduates' skill sets by providing students with learning opportunities and credentials that offer a head start on a career, postsecondary education, or both.
BVSD’s Accelerate programming and courses, are a pillar of the district’s Grad Plus framework, and are designed to empower students through relevant, rigorous academic and technical skills for career and college readiness. Accelerate courses are offered at both middle and high schools as well as at BVSD’s Technical Education Center, Apex.