Sign In

 

 

Monarch High Schoolhttps://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50{28e838a4-8015-4177-ac17-2576b5d1e514}Monarch High School329 Campus Drive Louisville, CO 80027http://moh.bvsd.org720.561.4200Phase 21998<img alt="" src="/projects/Project%20Profile%20Images/MonarchHS-photo-300x300.JPG" style="BORDER:0px solid;" />$10,586,740$800,000 included in budget

Latest Updates

 

 

July 2018https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=23https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=23{28e838a4-8015-4177-ac17-2576b5d1e514}July 2018Construction crews have made great progress at the school this month. Carpet has been removed from the corridors and crews are working on sanding and sealing the main hallway floors. New carpet will be installed in the academic wing hallways. HVAC upgrades are underway throughout the school, and the new chiller being installed at the K-8 should be operating at the start of school. Renovations in the band room and new black box theatre continue. This month data cables and furniture will be installed in the new distance learning lab in the Forum. New furniture for other areas throughout the school will be delivered and assembled in the coming weeks. Outside the school, the concrete pad for the new tennis courts has been poured and is awaiting application of new surface material and striping as are the old courts. The lower parking lot has been paved and striped. The metal building for the press box will be installed in the coming weeks. The project is on schedule to be substantially complete for the start of school in August. Administrative staff have moved to Louisville Middle School (1341 Main St.). They will return to the school with teachers on Aug. 8.
Construction Notice to Neighborshttps://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=20https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=20{28e838a4-8015-4177-ac17-2576b5d1e514}Construction Notice to Neighborshttps://bond.bvsd.org/projects/MonarchHS/Documents/Monarch%20construction%20start%20notification%20postcard%20text%20-%20web.pdf, http://bond.bvsd.org/projects/MonarchHS/Documents/Monarch%20construction%20start%20notification%20postcard%20text%20-%20web.pdf
Construction Kick-off Letter to Families and Staffhttps://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=19https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=19{28e838a4-8015-4177-ac17-2576b5d1e514}Construction Kick-off Letter to Families and Staffhttps://docs.google.com/document/d/1sHrtEwSZMTZT9IipwaRMsFjU-PJKI4l0hSSUqda-tX0/edit?usp=sharing, https://docs.google.com/document/d/1sHrtEwSZMTZT9IipwaRMsFjU-PJKI4l0hSSUqda-tX0/edit?usp=sharing

 

 

June 2018https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=22https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=22{28e838a4-8015-4177-ac17-2576b5d1e514}June 2018Now that school is out, construction crews have expanded to the entire site. Inside the school this month, flooring will be removed in the corridors. The main hallways will be finished with sealed concrete and carpet will be installed in the academic wing hallways. Demolition will begin in certain areas to prepare for HVAC upgrades and other work. Old classroom furniture will be removed early this month and replaced with new furniture at the end of the project. Outside the school, work continues on the 4 new tennis courts and the existing courts are being resurfaced. The foundation of the press box is complete. The lower parking lot will be paved this month. Roof repair will begin this month and there may be some associated odor. Administrative staff have moved to Louisville Middle School (1341 Main St.). The school will be closed for the summer, with limited access to the building and the site for specific activities.
January 2017https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=10https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=10{28e838a4-8015-4177-ac17-2576b5d1e514}January 2017Architect selection for this project is underway. The Design Advisory Team process is set to begin in February. Check back in the DAT section of this page for the meeting schedule and minutes.
April 2017https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=11https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=11{28e838a4-8015-4177-ac17-2576b5d1e514}April 2017Cuningham Group has been selected as the architect for the project. The Design Advisory Team will begin meeting in April. Follow the DAT link for meeting schedule and minutes.
Project Kick-off Notification to Neighborshttps://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=12https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=12{28e838a4-8015-4177-ac17-2576b5d1e514}Project Kick-off Notification to Neighborshttps://bond.bvsd.org/projects/MonarchHS/Documents/Monarch%20DAT%20notification%20postcard%20text%20-%20neighbor%20web.pdf, http://bond.bvsd.org/projects/MonarchHS/Documents/Monarch%20DAT%20notification%20postcard%20text%20-%20neighbor%20web.pdf
Project Kick-off Letter to Parentshttps://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=13https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=13{28e838a4-8015-4177-ac17-2576b5d1e514}Project Kick-off Letter to Parentshttps://bond.bvsd.org/projects/MonarchHS/Documents/Monarch%20High%20Parent%20DAT%20Kick%20Off%20Letter.pdf, http://bond.bvsd.org/projects/MonarchHS/Documents/Monarch%20High%20Parent%20DAT%20Kick%20Off%20Letter.pdf
June 2017https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=14https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=14{28e838a4-8015-4177-ac17-2576b5d1e514}June 2017The project team is working with the Design Advisory Team (DAT) to develop the schematic design. Follow the link to DAT meeting minutes. https://bond.bvsd.org/projects/MonarchHS/Pages/default.aspx#dat, http://bond.bvsd.org/projects/MonarchHS/Pages/default.aspx#dat
July 2017https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=15https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=15{28e838a4-8015-4177-ac17-2576b5d1e514}July 2017The project team is finalizing the schematic design. Follow the DAT link for Design Advisory Team meeting minutes.
October 2017https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=16https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=16{28e838a4-8015-4177-ac17-2576b5d1e514}October 2017The project team is finalizing the design. Follow the DAT link for design advisory team meeting minutes.
December 2017https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=17https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=17{28e838a4-8015-4177-ac17-2576b5d1e514}December 2017The project team is working on construction documents and planning for construction in summer 2018.
January 2018https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=18https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=18{28e838a4-8015-4177-ac17-2576b5d1e514}January 2018The project team is working on construction documents and planning for construction in summer 2018.
March 2018https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=21https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=21{28e838a4-8015-4177-ac17-2576b5d1e514}March 2018Construction will begin in March and be complete by August. The contractor will mobilize to the school site over spring break and will set up a staging area near the sand volleyball courts on the high school campus. Another construction area will be set up at Monarch PK-8 near the school’s gyms. During April and May, work will take place on the high school tennis courts and the air conditioning units at the PK-8. Once school is out, more extensive work will begin both inside and outside the buildings. The schools will be closed for the summer, with limited access to the building and the site for specific activities. Follow the links below for more information.
This project is scheduled to begin in Phase 2. https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=8https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=8{28e838a4-8015-4177-ac17-2576b5d1e514}This project is scheduled to begin in Phase 2.
There are no previous updates.https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=9https://bond.bvsd.org/projects/MonarchHS/Lists/Latest Updates/DispForm.aspx?ID=9{28e838a4-8015-4177-ac17-2576b5d1e514}There are no previous updates.

Project Details

Project Team
Project Manager

 

 

Charles Zachemskyhttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=9{28e838a4-8015-4177-ac17-2576b5d1e514}Charles Zachemskycharles.zachemsky@bvsd.org720-561-5954mailto:charles.zachemsky@bvsd.org, mailto:charles.zachemsky@bvsd.org

Architect

 

 

Cuningham Group Architecturehttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=19{28e838a4-8015-4177-ac17-2576b5d1e514}Cuningham Group Architecturehttp://www.cuningham.com/, http://www.cuningham.com/

Contractor

 

 

GE Johnsonhttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=12{28e838a4-8015-4177-ac17-2576b5d1e514}GE Johnsonhttps://gejohnson.com/, https://gejohnson.com/

Related Resources

 

 

Educational Facilities Master Planhttps://bond.bvsd.org/projects/MonarchHS/Lists/Related Resources/DispForm.aspx?ID=5https://bond.bvsd.org/projects/MonarchHS/Lists/Related Resources/DispForm.aspx?ID=5{28e838a4-8015-4177-ac17-2576b5d1e514}Educational Facilities Master Planhttps://bond.bvsd.org/masterplan/Documents/EdFacilityMasterPlan.pdf#page=63, http://bond.bvsd.org/masterplan/Documents/EdFacilityMasterPlan.pdf#page=63page

Details
Project Budget

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50{28e838a4-8015-4177-ac17-2576b5d1e514}$10,586,740

Innovation Budget

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50{28e838a4-8015-4177-ac17-2576b5d1e514}$800,000 included in budget

Bond Expenditures

 

 

Monarch High Schoolhttps://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50{28e838a4-8015-4177-ac17-2576b5d1e514}Monarch High Schoolhttps://bond.bvsd.org/financial/Documents/CurrentProgramExpenditures.pdf, Bond Program Expenditures

Project Expenditures

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50{28e838a4-8015-4177-ac17-2576b5d1e514}https://bond.bvsd.org/financial/Documents/CurrentProjectExpenditures.pdf, Project Expenditures

Sustainability Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50{28e838a4-8015-4177-ac17-2576b5d1e514}<div>Under development</div>

Energy Efficiency/Green Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50{28e838a4-8015-4177-ac17-2576b5d1e514}<div>Under development</div>

Educational Innovation Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=50{28e838a4-8015-4177-ac17-2576b5d1e514}<div class="ExternalClass75916FACBA304F33A60598DE1345415B"><div>The Monarch High School Innovation project will renovate the library to make it more interactive and flexible. The project also will create an audio/visual recording space. The project aligns with BVSD's six <a href="http://bvsdsuccesseffect.org/educational-innovation/"><div style="display:inline !important;"><strong>Innovation Guiding Principles.</strong></div></a></div><a href="http://bvsdsuccesseffect.org/educational-innovation/"><div><strong><br></strong></div></a><div><strong><a href="/educational-innovation/Pages/Monarch-High-School.aspx">Learn more</a></strong><br><br></div></div>

Design Advisory Team

​The Design Advisory Team (DAT) team includes teachers, staff, parents and community members who will work with the architects to develop the design for the project.​ The design advisory team will be created when the project begins. 

Staff Representatives

Autumn Francis - CTE
Mystayn Barnes - Language Arts
Melissa Vass - Math
Chuck Stephen - Music
Phil Bravo - Physical Education
Kathy Packard - Science 
Tom Hacker - Counselor
Mark Sibley - Athletic Director
Jerry Anderson - Principal (2017)
Neil Anderson - Principal (July 2017 - present)
Beatrice Gerrish - Librarian
Barbara Olsen - Support Staff

Parent Representative
Heather Balser

Student Representative
Levi Wood

Related Resources

 

 

Design Advisory Team Guidelineshttps://bond.bvsd.org/projects/MonarchHS/Lists/DAT Related Resources/DispForm.aspx?ID=5https://bond.bvsd.org/projects/MonarchHS/Lists/DAT Related Resources/DispForm.aspx?ID=5{28e838a4-8015-4177-ac17-2576b5d1e514}Design Advisory Team Guidelineshttps://bond.bvsd.org/projects/Documents/DATGuidelines-Revised2015.pdf, http://bond.bvsd.org/projects/Documents/DATGuidelines-Revised2015.pdfpage

DAT Meeting Schedule

DAT meetings are open for the public to observe, and there is an opportunity for public comment at each meeting. ​​

 

 

April 5 | 3:15 p.m.https://bond.bvsd.org/projects/MonarchHS/Lists/DAT Meetings List/DispForm.aspx?ID=1https://bond.bvsd.org/projects/MonarchHS/Lists/DAT Meetings List/DispForm.aspx?ID=1{28e838a4-8015-4177-ac17-2576b5d1e514}April 5 | 3:15 p.m.https://bond.bvsd.org/projects/MonarchHS/DATMeetingDocs/mm20170413%20DAT%2001%20CGA%2004-14_17.pdf, http://bond.bvsd.org/projects/MonarchHS/DATMeetingDocs/mm20170413%20DAT%2001%20CGA%2004-14_17.pdf
April 19 | 3:15 p.m.https://bond.bvsd.org/projects/MonarchHS/Lists/DAT Meetings List/DispForm.aspx?ID=2https://bond.bvsd.org/projects/MonarchHS/Lists/DAT Meetings List/DispForm.aspx?ID=2{28e838a4-8015-4177-ac17-2576b5d1e514}April 19 | 3:15 p.m.https://bond.bvsd.org/projects/MonarchHS/DATMeetingDocs/mm20170419%20DAT%2002%20CGA%2004-19_17.pdf, http://bond.bvsd.org/projects/MonarchHS/DATMeetingDocs/mm20170419%20DAT%2002%20CGA%2004-19_17.pdf
May 17 | 3:15 p.m.https://bond.bvsd.org/projects/MonarchHS/Lists/DAT Meetings List/DispForm.aspx?ID=4https://bond.bvsd.org/projects/MonarchHS/Lists/DAT Meetings List/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}May 17 | 3:15 p.m.

Timeline

 

 

Schematic Designhttps://bond.bvsd.org/projects/MonarchHS/Lists/Project Timeline/DispForm.aspx?ID=4https://bond.bvsd.org/projects/MonarchHS/Lists/Project Timeline/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}Schematic DesignMay 2017Completesuccess
Design Developmenthttps://bond.bvsd.org/projects/MonarchHS/Lists/Project Timeline/DispForm.aspx?ID=3https://bond.bvsd.org/projects/MonarchHS/Lists/Project Timeline/DispForm.aspx?ID=3{28e838a4-8015-4177-ac17-2576b5d1e514}Design DevelopmentAugust 2017Completesuccess
Construction Documentshttps://bond.bvsd.org/projects/MonarchHS/Lists/Project Timeline/DispForm.aspx?ID=2https://bond.bvsd.org/projects/MonarchHS/Lists/Project Timeline/DispForm.aspx?ID=2{28e838a4-8015-4177-ac17-2576b5d1e514}Construction DocumentsDecember 2017Completesuccess
Construction https://bond.bvsd.org/projects/MonarchHS/Lists/Project Timeline/DispForm.aspx?ID=1https://bond.bvsd.org/projects/MonarchHS/Lists/Project Timeline/DispForm.aspx?ID=1{28e838a4-8015-4177-ac17-2576b5d1e514}Construction April - Aug. 2018In Progressinfo

Images

    There are no items to show in this view of the "Construction Images" list.

    Scope of Work

    Facility Condition

    • Exterior building improvements such as repair/replace doors
    • Replace roof
    • Replace moveable partitions
    • Improvements to interior finishes such as carpet, flooring, ceiling tile and paint
    • Plumbing repair/replacement
    • HVAC repair
    • Intercom and clock system repair/replacement
    • Kitchen renovation and equipment upgrades
    • Replace gym bleachers
    • Site improvements such as paving and irrigation
    • Audio enhancement in every classroom**

    Program Compatibility 

    • Renovations to Music spaces

    Health and Physical Development

    • Replace field bleachers
    • Provide press box
    • Repair/replace athletic facilities such as baseball/softball fields and fixtures, football and soccer goals
    • Repair/add tennis courts
    • Modernize weight room
    • Provide multi-purpose fitness room

    Safety and Security

    • Install camera/intercom security system
    • Install electronic security controls
    • Install security partitions
    • Replace/add exterior cameras
    • Install interior security cameras (amended May 8, 2018)

    Sustainability

    • Upgrade lighting
    • Conduct retro-commissioning and repairs
    • Upgrade HVAC controls

    Innovation

    Monarch High School is eligible to receive up to $800,000 in additional funds to implement facility improvements that support innovative teaching methods.

    ** Not included in estimated project budget