Mesa Elementary Schoolhttps://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49{28e838a4-8015-4177-ac17-2576b5d1e514}Mesa Elementary School1575 Lehigh Street Boulder, CO 80305http://schools.bvsd.org/p12/mesa720.561.3000Phase 31966<img alt="" src="/projects/Project%20Profile%20Images/MesaES-photo-300x300.JPG" style="BORDER:0px solid;" />$8,444,002$200,000 included in budget

Latest Updates

 

 

June 2019https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=23https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=23{28e838a4-8015-4177-ac17-2576b5d1e514}June 2019With students and teachers out of the building for the summer, construction has expanded to the entire site. For the month of June, interior construction will be focused on asbestos abatement, demolition of some existing bathrooms, and the HVAC system. Prior to the end of school, electrical crews worked evening inside the building to get a head start on summer work. After demolition, crews will begin roughing-in the new HVAC, plumbing, and electrical systems. Outside on top of the building, crews will prepare for new mechanical HVAC units and take care of some minor roof replacement. On the playgrounds, crews are at work removing pea gravel and regrading the area to prepare for a new foundation and rubberized play surface. Some of the existing equipment will be reinstalled as well as some new pieces. Construction of a new preschool playground is underway. Just a reminder that the entire school site is closed for construction until early August.
Construction Kick-off Postcard to Neighborshttps://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=19https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=19{28e838a4-8015-4177-ac17-2576b5d1e514}Construction Kick-off Postcard to Neighborshttps://docs.google.com/document/d/1Va3pEUtb0aRUtwTladd7t9zk_dSkCOXwCVWGspMG39I/edit?usp=sharing, https://docs.google.com/document/d/1Va3pEUtb0aRUtwTladd7t9zk_dSkCOXwCVWGspMG39I/edit?usp=sharing
Construction Kick-off Letter to Families and Staffhttps://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=18https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=18{28e838a4-8015-4177-ac17-2576b5d1e514}Construction Kick-off Letter to Families and Staffhttps://docs.google.com/document/d/1cEoduw0T8ww_BFfFYJI_8GnJMDPi6hKUk7SvHK5Ygq4/edit?usp=sharing, https://docs.google.com/document/d/1cEoduw0T8ww_BFfFYJI_8GnJMDPi6hKUk7SvHK5Ygq4/edit?usp=sharing

 

 

May 24, 2019https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=22https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=22{28e838a4-8015-4177-ac17-2576b5d1e514}May 24, 2019Turner Construction has made great progress in the library makerspace. Crews have completed the wall framing and electrical rough-ins and now are starting to hang drywall on the ceiling and walls. In the coming week, they will have walls painted and flooring installed. This summer, they will expand their construction scope to include the building and the exterior site work (see link at bottom of the page for a summary of the construction scope). Monthly communications will be provided over the summer. We want to thank you for your patience and understanding with the preliminary construction work, and we look forward to a newly renovated school in the fall. Just a reminder, the school building and grounds will be closed for the summer. Mesa administrative staff will move to Creekside Elementary during construction. https://docs.google.com/document/d/1x86Nme2TidVwEaQNTBJhKql00SRmI62Af2E42WtCAmg/edit?usp=sharing, https://docs.google.com/document/d/1x86Nme2TidVwEaQNTBJhKql00SRmI62Af2E42WtCAmg/edit?usp=sharing
November 2018https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=16https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=16{28e838a4-8015-4177-ac17-2576b5d1e514}November 2018The project team is developing construction documents. Turner Construction has been selected as the general contractor. Follow the DAT link for project details.
April 2019https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=17https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=17{28e838a4-8015-4177-ac17-2576b5d1e514}April 2019Construction will begin in April and will be substantially complete by August. Initial work will occur after hours and will include above ceiling work and building investigations. Check back for updates.
Mesa Elementary Asbestos Abatement Information Letter | April 16, 2019https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=20https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=20{28e838a4-8015-4177-ac17-2576b5d1e514}Mesa Elementary Asbestos Abatement Information Letter | April 16, 2019https://docs.google.com/document/d/1-kk6Ze57T_Y6TJI5d2Wa7W09h_JxKJpjpRJagKTo9Rc/edit?usp=sharing, https://docs.google.com/document/d/1-kk6Ze57T_Y6TJI5d2Wa7W09h_JxKJpjpRJagKTo9Rc/edit?usp=sharing
October 2018https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=15https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=15{28e838a4-8015-4177-ac17-2576b5d1e514}October 2018The project team is working on Design Development. Follow the DAT link for meeting minutes.
Project Kick-off Letter to Familieshttps://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=12https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=12{28e838a4-8015-4177-ac17-2576b5d1e514}Project Kick-off Letter to Familieshttps://docs.google.com/document/d/1ypkA_Jo4oucfLCdxlmRSe-Hz_pTcjH9mVL-MwvQxDEY/edit?usp=sharing, https://docs.google.com/document/d/1ypkA_Jo4oucfLCdxlmRSe-Hz_pTcjH9mVL-MwvQxDEY/edit?usp=sharing
September 2018https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=14https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=14{28e838a4-8015-4177-ac17-2576b5d1e514}September 2018The project team is working on design development.
May 13, 2019https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=21https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=21{28e838a4-8015-4177-ac17-2576b5d1e514}May 13, 2019Turner Construction started working in the Mesa library this week. After all books and materials were packed last weekend, they began renovations to create the new makerspace area of the library. Construction crews will be working from 3:30 p.m. to 12 a.m. Monday through Friday. Work in the library over the next few weeks will include removing windows (for later reuse) and beginning ceiling and wall demolition. Once complete, they will begin framing walls, start electrical rough-ins and re-install the salvaged windows. Additional demolition work will begin in the boiler room when the weather is warm enough to shut down the boiler system. We appreciate the opportunity to begin the construction work early to help meet completion dates in August.https://docs.google.com/document/d/1_jz-1ERwxHDZrcRXbbuFNL7gib7Pc_GD7HnaozSO3PU/edit?usp=sharing, https://docs.google.com/document/d/1_jz-1ERwxHDZrcRXbbuFNL7gib7Pc_GD7HnaozSO3PU/edit?usp=sharing
June 2018https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=10https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=10{28e838a4-8015-4177-ac17-2576b5d1e514}June 2018Design work for this project will begin this summer. Check back for updates.
Project Kick-off Postcard to Neighborshttps://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=13https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=13{28e838a4-8015-4177-ac17-2576b5d1e514}Project Kick-off Postcard to Neighborshttps://bond.bvsd.org/projects/Mesa/Documents/Mesa%20Neighbor%20DAT%20Start%20Notification%20Postcard%20web.pdf, https://bond.bvsd.org/projects/Mesa/Documents/Mesa%20Neighbor%20DAT%20Start%20Notification%20Postcard%20web.pdf
This project is scheduled to begin in Phase 3. https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=8https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=8{28e838a4-8015-4177-ac17-2576b5d1e514}This project is scheduled to begin in Phase 3.
There are no previsous updates. https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=9https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=9{28e838a4-8015-4177-ac17-2576b5d1e514}There are no previsous updates.
August 2018https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=11https://bond.bvsd.org/projects/Mesa/Lists/Latest Updates/DispForm.aspx?ID=11{28e838a4-8015-4177-ac17-2576b5d1e514}August 2018The Design Advisory Team (DAT) is working with the architects to develop the project design. Follow the DAT link for meeting dates and minutes.

Project Details

Project Team
Project Manager

 

 

Katheryn Zeebhttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=44{28e838a4-8015-4177-ac17-2576b5d1e514}Katheryn Zeebkatheryn.zeeb@bvsd.org720.561.5109

Architect

 

 

Anderson Hallashttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=52{28e838a4-8015-4177-ac17-2576b5d1e514}Anderson Hallas

Contractor

 

 

Turnerhttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=40{28e838a4-8015-4177-ac17-2576b5d1e514}Turner

Related Resources

 

 

Educational Facilities Master Planhttps://bond.bvsd.org/projects/Mesa/Lists/Related Resources/DispForm.aspx?ID=5https://bond.bvsd.org/projects/Mesa/Lists/Related Resources/DispForm.aspx?ID=5{28e838a4-8015-4177-ac17-2576b5d1e514}Educational Facilities Master Planhttps://bond.bvsd.org/masterplan/Documents/EdFacilityMasterPlan.pdf#page=62, http://bond.bvsd.org/masterplan/Documents/EdFacilityMasterPlan.pdf#page=62page

Details
Project Budget

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49{28e838a4-8015-4177-ac17-2576b5d1e514}$8,444,002

Innovation Budget

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49{28e838a4-8015-4177-ac17-2576b5d1e514}$200,000 included in budget

Bond Expenditures

 

 

Mesa Elementary Schoolhttps://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49{28e838a4-8015-4177-ac17-2576b5d1e514}Mesa Elementary Schoolhttps://bond.bvsd.org/financial/Documents/CurrentProgramExpenditures.pdf, Bond Program Expenditures

Project Expenditures

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49{28e838a4-8015-4177-ac17-2576b5d1e514}https://bond.bvsd.org/financial/Documents/CurrentProjectExpenditures.pdf, Project Expenditures

Sustainability Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49{28e838a4-8015-4177-ac17-2576b5d1e514}<div>Under development</div>

Energy Efficiency/Green Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49{28e838a4-8015-4177-ac17-2576b5d1e514}<div>Under development</div>

Educational Innovation Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=49{28e838a4-8015-4177-ac17-2576b5d1e514}<div>Under development</div>

Design Advisory Team

​The Design Advisory Team (DAT) team includes teachers, staff, parents and community members who will work with the architects to develop the design for the project.​ The design advisory team will be created when the project begins. 

Staff 
Josh Baldner, Principal
Sarah Dutton-Swain, Specialist Teacher
Rachelle Krumpeck, 5th Grade Teacher
Arlene Gregersen, Teacher Librarian
Parents
Christin Whitco
  
​​Community​
Related Resources

 

 

Design Advisory Team Guidelineshttps://bond.bvsd.org/projects/Mesa/Lists/DAT Related Resources/DispForm.aspx?ID=5https://bond.bvsd.org/projects/Mesa/Lists/DAT Related Resources/DispForm.aspx?ID=5{28e838a4-8015-4177-ac17-2576b5d1e514}Design Advisory Team Guidelineshttps://bond.bvsd.org/projects/Documents/DATGuidelines-Revised2015.pdf, http://bond.bvsd.org/projects/Documents/DATGuidelines-Revised2015.pdfpage

DAT Meeting Schedule

DAT meetings are open for the public to observe, and there is an opportunity for public comment at each meeting. ​​

 

 

August 16, 2018 https://bond.bvsd.org/projects/Mesa/Lists/DAT Meetings List/DispForm.aspx?ID=1https://bond.bvsd.org/projects/Mesa/Lists/DAT Meetings List/DispForm.aspx?ID=1{28e838a4-8015-4177-ac17-2576b5d1e514}August 16, 2018 https://bond.bvsd.org/projects/Mesa/DATMeetingDocs/2018.08.16%20MESA%20DAT%201%20Meeting%20Minutes%20-%20DRAFT.pdf, https://bond.bvsd.org/projects/Mesa/DATMeetingDocs/2018.08.16%20MESA%20DAT%201%20Meeting%20Minutes%20-%20DRAFT.pdf
August 29, 2018 https://bond.bvsd.org/projects/Mesa/Lists/DAT Meetings List/DispForm.aspx?ID=2https://bond.bvsd.org/projects/Mesa/Lists/DAT Meetings List/DispForm.aspx?ID=2{28e838a4-8015-4177-ac17-2576b5d1e514}August 29, 2018 https://bond.bvsd.org/projects/Mesa/DATMeetingDocs/2018.08.29%20MESA%20DAT%202%20Meeting%20Minutes.pdf, https://bond.bvsd.org/projects/Mesa/DATMeetingDocs/2018.08.29%20MESA%20DAT%202%20Meeting%20Minutes.pdf
September 12, 2018https://bond.bvsd.org/projects/Mesa/Lists/DAT Meetings List/DispForm.aspx?ID=3https://bond.bvsd.org/projects/Mesa/Lists/DAT Meetings List/DispForm.aspx?ID=3{28e838a4-8015-4177-ac17-2576b5d1e514}September 12, 2018https://bond.bvsd.org/projects/Mesa/DATMeetingDocs/2018.09.12%20MESA%20DAT3%20Meeting%20Minutes%20-%20DRAFT.pdf, https://bond.bvsd.org/projects/Mesa/DATMeetingDocs/2018.09.12%20MESA%20DAT3%20Meeting%20Minutes%20-%20DRAFT.pdf
October 3, 2018https://bond.bvsd.org/projects/Mesa/Lists/DAT Meetings List/DispForm.aspx?ID=4https://bond.bvsd.org/projects/Mesa/Lists/DAT Meetings List/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}October 3, 2018https://bond.bvsd.org/projects/Mesa/DATMeetingDocs/2018.10.03%20MESA%20DAT%204%20Meeting%20Minutes.pdf, https://bond.bvsd.org/projects/Mesa/DATMeetingDocs/2018.10.03%20MESA%20DAT%204%20Meeting%20Minutes.pdf

Timeline

 

 

Schematic Design/Design Development | September 2018https://bond.bvsd.org/projects/Mesa/Lists/Project Timeline/DispForm.aspx?ID=1https://bond.bvsd.org/projects/Mesa/Lists/Project Timeline/DispForm.aspx?ID=1{28e838a4-8015-4177-ac17-2576b5d1e514}Schematic Design/Design Development | September 2018Completesuccess
Construction Documents | December 2018https://bond.bvsd.org/projects/Mesa/Lists/Project Timeline/DispForm.aspx?ID=2https://bond.bvsd.org/projects/Mesa/Lists/Project Timeline/DispForm.aspx?ID=2{28e838a4-8015-4177-ac17-2576b5d1e514}Construction Documents | December 2018Completesuccess
Construction | April - August 2019https://bond.bvsd.org/projects/Mesa/Lists/Project Timeline/DispForm.aspx?ID=3https://bond.bvsd.org/projects/Mesa/Lists/Project Timeline/DispForm.aspx?ID=3{28e838a4-8015-4177-ac17-2576b5d1e514}Construction | April - August 2019In Progressinfo

Images

    There are no items to show in this view of the "Construction Images" list.

    Scope of Work

    Facility Condition

    • Exterior building improvements such as repair/replace windows and doors
    • Replace roof
    • Restroom renovations
    • Replace interior doors
    • Improvements to interior finishes such as carpet, flooring, ceiling tile and paint
    • Asbestos abatement
    • HVAC system improvements
    • Electrical system improvements
    • Repair/replace fixtures such as casework
    • Upgrade parking lot/drop-off area
    • Audio enhancement in every classroom
    • Building-wide air conditioning (amended Feb. 27, 2019)

    Program Compatibility 

    • Provide adequate space for full-day kindergarten
    • Provide adequate space for preschool

    Health and Physical Development

    • Upgrade playground equipment and surface material

    Safety and Security

    • Install electronic security controls
    • Redesign main entry to provide more control over visitor access
    • Install security partitions
    • Install camera/intercom security system

    Sustainability

    • Replace aged boilers with efficient condensing type
    • Upgrade HVAC Controls
    • Upgrade lighting
    • Conduct retro-commissioning and repairs

    Innovation

    Mesa Elementary School is eligible to receive up to $200,000 in additional funds to implement facility improvements that support innovative teaching methods.