Lafayette Elementary Schoolhttps://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44{28e838a4-8015-4177-ac17-2576b5d1e514}Lafayette Elementary School101 North Bermont Avenue Lafayette, CO 80026http://schools.bvsd.org/p12/Lafayette720.561.8900Phase 31964<img alt="" src="/projects/Project%20Profile%20Images/LafayetteES-photo-300x300.JPG" style="BORDER:0px solid;" />$10,211,416$200,000 included in budget

Latest Updates

 

 

September 2019https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=35https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=35{28e838a4-8015-4177-ac17-2576b5d1e514}September 2019Construction is substantially complete. Scroll down for photos of the project.

 

 

Agosto 2019https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=33https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=33{28e838a4-8015-4177-ac17-2576b5d1e514}Agosto 2019El proyecto de renovación de la escuela se acerca a su fase final, y Turner Construction y el personal escolar están trabajando intensamente para dejar la escuela lista para el regreso de los estudiantes. La transformación experimentada por la escuela gracias a las obras del verano es espectacular y los cambios realizados ayudarán a que la escuela se vea, se viva y funcione mejor. Aunque el lunes las obras habrán básicamente terminado y el edificio se considerará seguro, cómodo y listo para los estudiantes, todavía quedarán algunos trabajos en marcha que se adelantarán por las tardes y durante los fines de semana fuera del horario escolar. Se han realizado obras importantes en el recinto escolar y está programado que el material de goma de la superficie del patio de recreo se instale esta semana. Cualquier área que no esté preparada para el tránsito de estudiantes quedará marcada mediante vallas anaranjadas. A excepción de la cafetería, ¡vamos a empezar el año con aire acondicionado en toda la escuela! (Atención: es parte de la política del BVSD no instalar aire acondicionado en los gimnasios). El aire acondicionado de la cafetería necesita ciertas labores imprevistas de modernización y la pared de la cafetería del lado este permanecerá en obras entrado el año escolar. Se utilizarán paneles temporales para separar esta zona. Tenga en cuenta que tomará cierto tiempo hasta que el nuevo sistema de calefacción y aire acondicionado funcione de manera óptima, y hasta que quede ajustado se registrarán problemas de calor/frío. Durante el verano, la dirección del BVSD decidió mantener el edificio modular y convertirlo en espacio para reuniones del Distrito. Agradecemos la paciencia, comprensión y cooperación demostrada por toda la comunidad de la Escuela Primaria Lafayette durante el desarrollo de este proyecto. Agradecemos, también, los fondos invertidos en la escuela por parte de los contribuyentes del BVSD, los cuales beneficiarán a estudiantes y maestros durante los años venideros. https://drive.google.com/file/d/1p8HR1pb37iNdNo4J0z20uCLQNMeIooB6/view?usp=sharing, https://drive.google.com/file/d/1p8HR1pb37iNdNo4J0z20uCLQNMeIooB6/view?usp=sharing
24 de mayo de 2019https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=27https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=27{28e838a4-8015-4177-ac17-2576b5d1e514}24 de mayo de 2019Turner Construction sigue trabajando en el patio de recreo intermedio. Hace poco terminaron de instalar el alcantarillado del nuevo patio de recreo y están empezando a formar y verter el concreto para los cimientos. Dentro del edificio, los equipos han estado trabajando durante las tardes para instalar el cableado eléctrico dentro del techo y durante los próximos días instalarán las luces en el nuevo gimnasio. Estamos agradecidos de la oportunidad de comenzar la construcción temprano, ya que nos ayudará a terminar antes de que las clases comiencen en agosto. Les recordamos que la escuela y los espacios exteriores estarán cerrados durante el verano. El personal administrativo de Lafayette se trasladará a la primaria Pioneer durante la construcción. https://docs.google.com/document/d/1sM-98Lg7BjRH9b9JMeBT7CIXm1DqU-s7KSeLnjoF0E4/edit?usp=sharing, https://docs.google.com/document/d/1sM-98Lg7BjRH9b9JMeBT7CIXm1DqU-s7KSeLnjoF0E4/edit?usp=sharing
Carta de Inicio de Construcciónhttps://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=19https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=19{28e838a4-8015-4177-ac17-2576b5d1e514}Carta de Inicio de Construcciónhttps://docs.google.com/document/d/1jUf5TBz59KG9XiX-5h6XMvq5tUiSqluU9VLKnHx2ZGI/edit?usp=sharing, https://docs.google.com/document/d/1jUf5TBz59KG9XiX-5h6XMvq5tUiSqluU9VLKnHx2ZGI/edit?usp=sharing
29 de abril de 2019https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=25https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=25{28e838a4-8015-4177-ac17-2576b5d1e514}29 de abril de 2019Turner Construction se ha trasladado al sitio y ha establecido una zona de construcción alrededor del patio de recreo para estudiantes mayores. A lo largo de las últimas semanas, los equipos se han mantenido ocupados sacando el equipo de recreo existente y el asfalto viejo. El trabajo ha disminuido recientemente para limitar interrupciones a los exámenes de CMAS. Durante las próximas semanas, los trabajadores cavarán pequeñas zanjas en el asfalto cerca del patio de recreo para facilitar el drenaje. Las zanjas se taparán temporalmente con tableros de madera, hasta que se puedan volver a llenar con asfalto en el verano. https://docs.google.com/document/d/1Q5880TsuAQHmDcrq0zghTVC-UJaY05mvuTCiPt_CMkQ/edit?usp=sharing, https://docs.google.com/document/d/1Q5880TsuAQHmDcrq0zghTVC-UJaY05mvuTCiPt_CMkQ/edit?usp=sharing
Nueva fecha de inicio del año escolar 2019-20 de la Primaria Lafayettehttps://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=22https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=22{28e838a4-8015-4177-ac17-2576b5d1e514}Nueva fecha de inicio del año escolar 2019-20 de la Primaria LafayetteDespués de considerar detenidamente la cantidad de trabajo que hay que terminar y el tiempo que tendremos disponible para hacerlo mientras que los estudiantes y empleados están fuera del edificio durante el verano, decidimos demorar el inicio del año escolar 2019-20 por tres días. Un factor grande detrás de esta decisión es la gran cantidad de asbesto que se eliminará durante el proyecto de construcción. Aunque el trabajo comenzará el momento que termina el año escolar, tomará bastante tiempo completarlo. Además, no se podrá hacer más construcción hasta que termine la eliminación de asbesto. Al demorar el inicio del nuevo año escolar, podremos disponer del tiempo adicional necesario para terminar el trabajo y permitir un comienzo más tranquilo del nuevo año. https://docs.google.com/document/d/1w6n-t74CyOhgGY_4tyf2J7ikrgXSCJwSvwX3YFOmShI/edit?usp=sharing, https://docs.google.com/document/d/1w6n-t74CyOhgGY_4tyf2J7ikrgXSCJwSvwX3YFOmShI/edit?usp=sharing
Junio 2019https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=30https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=30{28e838a4-8015-4177-ac17-2576b5d1e514}Junio 2019Después de mover los muebles y materiales al final del año escolar, Turner Construction ha comenzado a hacer todo el trabajo para las renovaciones en Lafayette. En este momento, los equipos están trabajando dentro del edificio para eliminar asbesto, reemplazar las luces del gimnasio, instalar el nuevo sistema de alarma en caso de incendios y extraer el sistema de calefacción, ventilación y aire acondicionado. También están trabajando afuera del edificio, vertiendo concreto para el nuevo alcantarillado y los cimientos del patio de recreo intermedio, reemplazando el techo en las secciones más antiguas del edificio, removiendo el asfalto para construir una nueva zona de llegada de autobuses en frente de la escuela y preparándose para instalar las nuevas ventanas y el sistema de calefacción, ventilación y aire acondicionado. Se hará mucho trabajo durante el mes de junio, dentro y fuera del edificio, y queremos recordar a todos que el edificio y las instalaciones están cerradas durante el verano. Para su propia seguridad, por favor no entren a la zona de construcción.
Julio de 2019https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=31https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=31{28e838a4-8015-4177-ac17-2576b5d1e514}Julio de 2019¡La Escuela Primaria Lafayette es un lugar muy ocupado en estos días! Turner Construction, el contratista general para el proyecto de renovaciones, ha progresado mucho durante el verano. Completaron la eliminación de asbesto en el edificio y demolieron porciones grandes de las paredes exteriores de los salones como preparación para instalar los nuevos ventiladores con aire acondicionado. La reconstrucción de las paredes está progresando y será necesario contratar a varios trabajadores especializados como plomeros, electricistas, instaladores de ventanas, mamposteros, subcontratistas mecánicos, carpinteros e instaladores de pisos. Vertieron concreto para la zona de llegada de autobuses y los alcantarillados, junto con otros elementos del patio de recreo intermedio. Los equipos están ocupados removiendo las secciones más antiguas del techo como preparación para instalar el techo nuevo durante las próximas semanas. El techo nuevo y los otros componentes del proyecto, como ventanas nuevas, luces nuevas en el gimnasio y el nuevo sistema de calefacción, ventilación y aire acondicionado, servirán para mejorar la eficiencia de la escuela en el uso de energía. Los baños se están renovando para mejorar la estética y la accesibilidad para individuos con discapacidades. Se ha quitado la alfombra de varios lugares del edificio y se reemplazará con alfombra nueva. Los técnicos también están trabajando mucho en el espacio encima del cielo raso, instalando cantidades grandes de alambres y cables de fibra óptica para el aire acondicionado, mejoras al sistema de alarma en caso de incendios y los sistemas de comunicación. ¡Los estudiantes y empleados pueden esperar grandes cambios cuando regresen en agosto!
August 2019https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=34https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=34{28e838a4-8015-4177-ac17-2576b5d1e514}August 2019The renovation project is moving into the final stages, and Turner Construction and school staff are busily working to prepare for the return of students. The transformation of the school from the work this summer is amazing, and there are exciting changes that will help the school look, feel, and perform better. While construction will be substantially complete and the building will be safe, comfortable, and ready for students on Monday, there will still be some ongoing work, which will take place evenings and weekends outside of school hours. There was a significant amount of work that occurred on the grounds around the school, and the rubberized surface material for the playground is scheduled to be installed this week. Any areas that are not ready for student traffic will be designated as off-limits with orange fencing. Except for the cafeteria, we will start the year with air conditioning throughout the school! (Note, it is BVSD’s practice not to air condition gyms.) The air conditioning unit for the cafeteria will require some unexpected retrofit work, and the east wall of the cafeteria will be under construction into the school year. The area will be partitioned with temporary walls. Please keep in mind, the new HVAC system will take some time to get fully adjusted, and there will be some hot/cold issues while we work to get it dialed in. Over the summer, district leadership decided to keep the modular building and convert it to district meeting space. We appreciate the patience, understanding, and cooperation of the entire Lafayette Elementary community through this project. We are grateful for the investment of BVSD taxpayers in the school which will benefit students and teachers for many years to come. https://docs.google.com/document/d/1Os-dzpI6wVQAIInDjeh2VrfxCAbmFwRwxvj8BGoMLLY/edit?usp=sharing, https://docs.google.com/document/d/1Os-dzpI6wVQAIInDjeh2VrfxCAbmFwRwxvj8BGoMLLY/edit?usp=sharing
November 2018https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=16https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=16{28e838a4-8015-4177-ac17-2576b5d1e514}November 2018The project team is working to have construction documents ready in December. Turner Construction has been selected as the contractor for the project. Follow the DAT link to meeting minutes for project details.
May 23, 2019https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=28https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=28{28e838a4-8015-4177-ac17-2576b5d1e514}May 23, 2019Turner Construction continues to work on the intermediate playground. They recently completed a storm drain installation on the playground and are now starting to form and pour concrete for the foundation of the new playground. Inside the building, crews are working evenings to install above ceiling electrical wiring and are scheduled to install new gym lighting in the coming days. We appreciate the opportunity to start the construction work early to help us meet the August school start date. Just a reminder, the school building and grounds will be closed for the summer. Lafayette administrative staff will move to Pioneer Elementary during construction.
October 2018https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=15https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=15{28e838a4-8015-4177-ac17-2576b5d1e514}October 2018The project team is working on design development. Follow the DAT link for design advisory team meeting minutes and dates. ​
June 2019https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=29https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=29{28e838a4-8015-4177-ac17-2576b5d1e514}June 2019After a successful furniture and materials move at the end of the school year, construction has expanded to the entire site. Currently, crews are working on the interior to remove asbestos, replace gym lighting, install the new fire alarm system, and remove the existing HVAC system. Outside, crews continue to work on the intermediate playground pouring new curbing and foundations, replace the roof on the older sections of the building, remove asphalt to prepare for a new bus loop at the front of the school, and prepare for new window replacements and HVAC installation. The month of June will see a lot of activity in and around the school,  and we would like to remind you that the site and building are closed for the summer. For your own safety, please do not enter the construction site. Watch for another update next month. Enjoy your summer!
March 2019https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=17https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=17{28e838a4-8015-4177-ac17-2576b5d1e514}March 2019Turner Construction will mobilize to the site over Spring Break. Read the Construction Kick-off Letter for more information about what to expect.
Construction Kick-off Letter to Families and Staffhttps://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=18https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=18{28e838a4-8015-4177-ac17-2576b5d1e514}Construction Kick-off Letter to Families and Staffhttps://docs.google.com/document/d/1I8KxR_3JeXMjtAR5JXGwfhW48gl8IPr9CeXG2v-q0qo/edit?usp=sharing, https://docs.google.com/document/d/1I8KxR_3JeXMjtAR5JXGwfhW48gl8IPr9CeXG2v-q0qo/edit?usp=sharing
April 29, 2019https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=26https://bond.bvsd.org/projects/Lafayette/Lists/Latest Updates/DispForm.aspx?ID=26{28e838a4-8015-4177-ac17-2576b5d1e514}April 29, 2019Turner Construction has mobilized to the site and established a construction area around the intermediate playground. Over the past few weeks, crews have been busy removing the existing playground equipment and old asphalt. Due to recent CMAS testing, work has slowed to minimize disruption. In the coming weeks, crews will dig small trenches in the asphalt by the intermediate playground for drainage. The trenches will be covered temporarily with plywood until asphalt can be poured back this summer. https://docs.google.com/document/d/1vDujeyzkziduK-wpEA0_-Us8ThFyR-YjYDatEElZZ9U/edit?usp=sharing, https://docs.google.com/document/d/1vDujeyzkziduK-wpEA0_-Us8ThFyR-YjYDatEElZZ9U/edit?usp=sharing

Project Details

Project Team
Project Manager

 

 

Gene Temansonhttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=55{28e838a4-8015-4177-ac17-2576b5d1e514}Gene Temanson

Architect

 

 

Wold Architects and Engineershttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=31{28e838a4-8015-4177-ac17-2576b5d1e514}Wold Architects and Engineershttp://www.woldae.com/, http://www.woldae.com/

Contractor

 

 

Turnerhttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=40{28e838a4-8015-4177-ac17-2576b5d1e514}Turner

Related Resources

 

 

Educational Facilities Master Planhttps://bond.bvsd.org/projects/Lafayette/Lists/Related Resources/DispForm.aspx?ID=5https://bond.bvsd.org/projects/Lafayette/Lists/Related Resources/DispForm.aspx?ID=5{28e838a4-8015-4177-ac17-2576b5d1e514}Educational Facilities Master Planhttps://bond.bvsd.org/masterplan/Documents/EdFacilityMasterPlan.pdf#page=57, http://bond.bvsd.org/masterplan/Documents/EdFacilityMasterPlan.pdf#page=57page

Details
Project Budget

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44{28e838a4-8015-4177-ac17-2576b5d1e514}$10,211,416

Innovation Budget

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44{28e838a4-8015-4177-ac17-2576b5d1e514}$200,000 included in budget

Bond Expenditures

 

 

Lafayette Elementary Schoolhttps://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44{28e838a4-8015-4177-ac17-2576b5d1e514}Lafayette Elementary Schoolhttps://bond.bvsd.org/financial/Documents/CurrentProgramExpenditures.pdf, Bond Program Expenditures

Project Expenditures

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44{28e838a4-8015-4177-ac17-2576b5d1e514}https://bond.bvsd.org/financial/Documents/CurrentProjectExpenditures.pdf, Project Expenditures

Sustainability Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44{28e838a4-8015-4177-ac17-2576b5d1e514}<div>Under development</div>

Energy Efficiency/Green Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44{28e838a4-8015-4177-ac17-2576b5d1e514}<div>Under development</div>

Educational Innovation Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=44{28e838a4-8015-4177-ac17-2576b5d1e514}<div>Under development</div>

Design Advisory Team

​The Design Advisory Team (DAT) team includes teachers, staff, parents and community members who will work with the architects to develop the design for the project.​ The design advisory team will be created when the project begins. 

Staff 
Stephanie Jackman, Principal
Jennifer Weaver, ILC Teacher
Parents

Alison Fischer, parent and 17-18 instructional para
Keenan Albenberg, parent
Tanner Dayhoff, parent and BVSD Principal

  
​​Community​
Related Resources

 

 

Design Advisory Team Guidelineshttps://bond.bvsd.org/projects/Lafayette/Lists/DAT Related Resources/DispForm.aspx?ID=5https://bond.bvsd.org/projects/Lafayette/Lists/DAT Related Resources/DispForm.aspx?ID=5{28e838a4-8015-4177-ac17-2576b5d1e514}Design Advisory Team Guidelineshttps://bond.bvsd.org/projects/Documents/DATGuidelines-Revised2015.pdf, http://bond.bvsd.org/projects/Documents/DATGuidelines-Revised2015.pdfpage

DAT Meeting Schedule

DAT meetings are open for the public to observe, and there is an opportunity for public comment at each meeting. ​​

 

 

June 19, 2018 | 1 - 3 p.m.https://bond.bvsd.org/projects/Lafayette/Lists/DAT Meetings List/DispForm.aspx?ID=1https://bond.bvsd.org/projects/Lafayette/Lists/DAT Meetings List/DispForm.aspx?ID=1{28e838a4-8015-4177-ac17-2576b5d1e514}June 19, 2018 | 1 - 3 p.m.https://bond.bvsd.org/projects/Lafayette/DATMeetingDocs/6.19.18%20DAT%201.pdf, https://bond.bvsd.org/projects/Lafayette/DATMeetingDocs/6.19.18%20DAT%201.pdf
August 14, 2018 | 2 - 4 p.m.https://bond.bvsd.org/projects/Lafayette/Lists/DAT Meetings List/DispForm.aspx?ID=2https://bond.bvsd.org/projects/Lafayette/Lists/DAT Meetings List/DispForm.aspx?ID=2{28e838a4-8015-4177-ac17-2576b5d1e514}August 14, 2018 | 2 - 4 p.m.https://bond.bvsd.org/projects/Lafayette/DATMeetingDocs/LES%208.14.18%20DAT%202.pdf, https://bond.bvsd.org/projects/Lafayette/DATMeetingDocs/LES%208.14.18%20DAT%202.pdf
September 11, 2018 | 2:45 - 4:45 p.m.https://bond.bvsd.org/projects/Lafayette/Lists/DAT Meetings List/DispForm.aspx?ID=3https://bond.bvsd.org/projects/Lafayette/Lists/DAT Meetings List/DispForm.aspx?ID=3{28e838a4-8015-4177-ac17-2576b5d1e514}September 11, 2018 | 2:45 - 4:45 p.m.https://bond.bvsd.org/projects/Lafayette/DATMeetingDocs/9.11.18%20DAT%203.pdf, https://bond.bvsd.org/projects/Lafayette/DATMeetingDocs/9.11.18%20DAT%203.pdf
October 3, 2018 | 2:45 - 4:45 p.m.https://bond.bvsd.org/projects/Lafayette/Lists/DAT Meetings List/DispForm.aspx?ID=5https://bond.bvsd.org/projects/Lafayette/Lists/DAT Meetings List/DispForm.aspx?ID=5{28e838a4-8015-4177-ac17-2576b5d1e514}October 3, 2018 | 2:45 - 4:45 p.m.https://bond.bvsd.org/projects/Lafayette/DATMeetingDocs/10.3.18%20DAT%204.pdf, https://bond.bvsd.org/projects/Lafayette/DATMeetingDocs/10.3.18%20DAT%204.pdf
November 13, 2018 | 2:45 - 4:45 p.m.https://bond.bvsd.org/projects/Lafayette/Lists/DAT Meetings List/DispForm.aspx?ID=4https://bond.bvsd.org/projects/Lafayette/Lists/DAT Meetings List/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}November 13, 2018 | 2:45 - 4:45 p.m.

Timeline

 

 

Schematic Design | September 2018https://bond.bvsd.org/projects/Lafayette/Lists/Project Timeline/DispForm.aspx?ID=1https://bond.bvsd.org/projects/Lafayette/Lists/Project Timeline/DispForm.aspx?ID=1{28e838a4-8015-4177-ac17-2576b5d1e514}Schematic Design | September 2018Completesuccess
Design Development | October 2018https://bond.bvsd.org/projects/Lafayette/Lists/Project Timeline/DispForm.aspx?ID=2https://bond.bvsd.org/projects/Lafayette/Lists/Project Timeline/DispForm.aspx?ID=2{28e838a4-8015-4177-ac17-2576b5d1e514}Design Development | October 2018Completesuccess
Construction Documents | December 2018https://bond.bvsd.org/projects/Lafayette/Lists/Project Timeline/DispForm.aspx?ID=3https://bond.bvsd.org/projects/Lafayette/Lists/Project Timeline/DispForm.aspx?ID=3{28e838a4-8015-4177-ac17-2576b5d1e514}Construction Documents | December 2018Completesuccess
Construction Start | March 2018https://bond.bvsd.org/projects/Lafayette/Lists/Project Timeline/DispForm.aspx?ID=4https://bond.bvsd.org/projects/Lafayette/Lists/Project Timeline/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}Construction Start | March 2018Completeinfo

Images

    There are no items to show in this view of the "Construction Images" list.

    Scope of Work

    Facility Condition

    • Exterior building improvements such as repair/replace windows and doors
    • Repair roof
    • Restroom renovations
    • Replace interior doors
    • Asbestos abatement
    • Electrical system upgrades including emergency generator
    • Communications and clock system improvements
    • HVAC system improvements
    • Site improvements such as paving and drainage
    • Audio enhancement in every classroom
    • Building-wide air conditioning (amended Feb. 27, 2019)

    Program Compatibility 

    • Provide adequate space for full-day kindergarten
    • Provide adequate space for preschool
    • Provide adequate Special Education space

    Health and Physical Development

    • Upgrade playground equipment and surface material

    Safety and Security

    • Install electronic security controls
    • Install security partitions
    • Install camera/intercom security system
    • Redesign main entry to provide more control over visitor access
    • Improve parking lot and exterior lighting

    Sustainability

    • Conduct retro-commissioning and repairs
    • Upgrade lighting

    Innovation

    Lafayette Elementary School is eligible to receive up to $200,000 in additional funds to implement facility improvements that support innovative teaching methods.