Eisenhower Elementary Schoolhttps://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30{28e838a4-8015-4177-ac17-2576b5d1e514}Eisenhower Elementary School1220 Eisenhower Drive Boulder, CO 80303http://schools.bvsd.org/p12/eisenhower720.561.6700Phase 21971<img alt="" src="/projects/Project%20Profile%20Images/eisenhower%20ES300X300.jpg" style="BORDER:0px solid;" />$6,871,579$200,000 included in budget

Latest Updates

 

 

Eisenhower Opening Day Delayedhttps://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=26https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=26{28e838a4-8015-4177-ac17-2576b5d1e514}Eisenhower Opening Day DelayedEisenhower Elementary’s first day of school is being delayed until Monday, Aug. 20. Safety is a top priority in the Boulder Valley School District. When the Operations team and Superintendent visited the building on Sunday, it was clear that the building will not pass state inspections for student and staff safety in time to open Aug. 15. Childcare will be available free of charge to parents who require the services at Mapleton Early Childhood Center. The SAC and KE program will also be available regular times. Transportation will be provided. Follow the link below to sign up for childcare. The Meet the Teacher event will now be held on Thursday, August 16 starting at 4:30 p.m., outside of Eisenhower. We regret the impact that this will have on our families. Thank you for your understanding and patience. https://docs.google.com/forms/d/e/1FAIpQLSfuWLgXOzzhRJHgb43xBVYKfiuKFYCQbQKm3IuRUJBwVdKqyA/viewform?c=0&w=1, Sign Up For Childcare



 

 

July 2018https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=24https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=24{28e838a4-8015-4177-ac17-2576b5d1e514}July 2018Himmelman Construction continues to make progress on the renovation work at Eisenhower. During the month of June, the exterior renovation focused on the installation of a new roofing system and site work demolition. On the interior, crews removed existing concrete floors in the kitchen and bathrooms to prepare the rooms for new plumbing configurations and finishes. In addition, tile flooring in the hallways has been removed and electrical and mechanical upgrades have started. The month of July will see a sizeable shift from demolition and site preparation to reconstruction of the building spaces both indoor and outdoor. We look forward to the completion of the roofing system, installation of new flooring and fresh paint throughout, updated restrooms, new preschool rooms and repaved parking lot.
June 2018https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=23https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=23{28e838a4-8015-4177-ac17-2576b5d1e514}June 2018Himmelman Construction has been busily getting started on both the exterior and interior renovation work. The exterior work began with roof replacement and the removal of old concrete for the new bus loop. The interior renovation work has started with asbestos abatement, restroom and classroom renovations, above-ceiling HVAC work and preparation for the new boilers. Other renovations that will occur this summer include adding an innovation space and redesigning interior space for two preschool classrooms. The administration offices have been temporarily relocated to Douglass Elementary School (840 75th Street, Boulder) until August. We are looking forward to a newly renovated Eisenhower Elementary school! PLEASE NOTE: The school and school grounds are closed for the summer. For your own safety, please do not enter the construction site, even after hours
February 2017https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=10https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=10{28e838a4-8015-4177-ac17-2576b5d1e514}February 2017Architect selection is underway for this project. The Design Advisory Team (DAT) process is planned to begin in March. The DAT meeting schedule and minutes will be posted in the DAT section below.
March 2017https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=11https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=11{28e838a4-8015-4177-ac17-2576b5d1e514}March 2017Anderson Hallas has been selected as the architect for this project. The Design Advisory Team (DAT) process is planned to begin in April. The DAT meeting schedule is posted in the DAT section below. Meeting minutes will be posted here as well.
Project Kick-off Notification to Neighborshttps://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=12https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=12{28e838a4-8015-4177-ac17-2576b5d1e514}Project Kick-off Notification to Neighborshttps://bond.bvsd.org/projects/Eisenhower/Documents/Eisenhower%20Neighbor%20DAT%20Start%20Notification%20Postcard%20text.pdf, http://bond.bvsd.org/projects/Eisenhower/Documents/Eisenhower%20Neighbor%20DAT%20Start%20Notification%20Postcard%20text.pdf
Project Kick-off Letter to Parentshttps://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=13https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=13{28e838a4-8015-4177-ac17-2576b5d1e514}Project Kick-off Letter to Parentshttps://bond.bvsd.org/projects/Eisenhower/Documents/Eisenhower%20Parent%20DAT%20Kick%20Off%20Letter.pdf, http://bond.bvsd.org/projects/Eisenhower/Documents/Eisenhower%20Parent%20DAT%20Kick%20Off%20Letter.pdf
May 2017https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=14https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=14{28e838a4-8015-4177-ac17-2576b5d1e514}May 2017The project team is working with the DAT to develop the schematic design.
Julyhttps://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=15https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=15{28e838a4-8015-4177-ac17-2576b5d1e514}JulyThe project team is working on design development. Follow the "DAT" link for design advisory team meeting minutes and schedule.
August 2017https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=16https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=16{28e838a4-8015-4177-ac17-2576b5d1e514}August 2017The project team is working on design development. Follow the "DAT" link for design advisory team meeting minutes and schedule. ​
September 2017https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=17https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=17{28e838a4-8015-4177-ac17-2576b5d1e514}September 2017The project team is working on design development documents. When design development is complete, the team will make a final presentation to the DAT.
December 2017https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=18https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=18{28e838a4-8015-4177-ac17-2576b5d1e514}December 2017The project team is developing construction documents and planning for construction this summer.
January 2018https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=19https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=19{28e838a4-8015-4177-ac17-2576b5d1e514}January 2018The project team is developing construction documents and planning for construction this summer. ​
March 2018https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=20https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=20{28e838a4-8015-4177-ac17-2576b5d1e514}March 2018The project team is finalizing construction documents and planning for construction this summer. ​
Construction Letter to Familieshttps://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=21https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=21{28e838a4-8015-4177-ac17-2576b5d1e514}Construction Letter to Familieshttps://docs.google.com/document/d/1Ky1O9HsznIlwRQUmPnQiJnk-L3TRqZMCgDRDVaDxll4/edit?usp=sharing, https://docs.google.com/document/d/1Ky1O9HsznIlwRQUmPnQiJnk-L3TRqZMCgDRDVaDxll4/edit?usp=sharing
April 2018https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=22https://bond.bvsd.org/projects/Eisenhower/Lists/Latest Updates/DispForm.aspx?ID=22{28e838a4-8015-4177-ac17-2576b5d1e514}April 2018Asbestos abatement was completed over Spring Break. Construction will begin in May and be complete by August. Check back for ongoing updates.

Project Details

Project Team
Project Manager

 

 

Marion Hammondhttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=15{28e838a4-8015-4177-ac17-2576b5d1e514}Marion Hammondmarion.hammond@bvsd.org720-561-5081mailto:marion.hammond@bvsd.org, mailto:marion.hammond@bvsd.org

Architect

 

 

Anderson Hallashttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=52{28e838a4-8015-4177-ac17-2576b5d1e514}Anderson Hallas

Contractor

 

 

Himmelman Constructionhttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=47{28e838a4-8015-4177-ac17-2576b5d1e514}Himmelman Construction

Related Resources

 

 

Educational Facilities Master Planhttps://bond.bvsd.org/projects/Eisenhower/Lists/Related Resources/DispForm.aspx?ID=5https://bond.bvsd.org/projects/Eisenhower/Lists/Related Resources/DispForm.aspx?ID=5{28e838a4-8015-4177-ac17-2576b5d1e514}Educational Facilities Master Planhttps://bond.bvsd.org/masterplan/Documents/EdFacilityMasterPlan.pdf#page=41, http://bond.bvsd.org/masterplan/Documents/EdFacilityMasterPlan.pdf#page=41page

Details
Project Budget

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30{28e838a4-8015-4177-ac17-2576b5d1e514}$6,871,579

Innovation Budget

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30{28e838a4-8015-4177-ac17-2576b5d1e514}$200,000 included in budget

Bond Expenditures

 

 

Eisenhower Elementary Schoolhttps://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30{28e838a4-8015-4177-ac17-2576b5d1e514}Eisenhower Elementary Schoolhttps://bond.bvsd.org/financial/Documents/CurrentProgramExpenditures.pdf, Bond Program Expenditures

Project Expenditures

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30{28e838a4-8015-4177-ac17-2576b5d1e514}https://bond.bvsd.org/financial/Documents/CurrentProjectExpenditures.pdf, Project Expenditures

Sustainability Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30{28e838a4-8015-4177-ac17-2576b5d1e514}<div>Under development</div>

Energy Efficiency/Green Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30{28e838a4-8015-4177-ac17-2576b5d1e514}<div>Under development</div>

Educational Innovation Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=30{28e838a4-8015-4177-ac17-2576b5d1e514}<div class="ExternalClassD1C2D2485A67490CAC638B01332DA9C3"><p>The Eisenhower Innovation project will invest in new classroom furniture and a new innovation/maker space. The school's current furniture is heavy and bulky and hard to move. The new furniture is intended to support flexibility in instruction by allowing teachers and students to reconfigure learning spaces easily depending on instructional needs. The maker space will give kids a place where they can create and inquire.<br></p><a href="/educational-innovation/Pages/Eisenhower-Elementary-Innovation-Project.aspx"><p><strong>Learn more</strong></p></a><p><br></p></div>

Design Advisory Team

​The Design Advisory Team (DAT) team includes teachers, staff, parents and community members who will work with the architects to develop the design for the project.​ 

Staff 

Megan Haseloh, 5th grade teacher
Sam Palsmeier, Library
Toni Estoque, Kindergarten teacher
Arti Courson, Special Education
Jenni Leavitt, 3rd grade teacher
Lisa Dings, Principal's Assistant
Marti Hirsch, Paraprofessional
Julie Parks, ELD
Brady Stroup, Principal

Parents
Brendan Ash
Shane Brown
Clare Brandt
Dana Michel

  
Community
Steve Barta (neighbor)

Related Resources

 

 

Design Advisory Team Guidelineshttps://bond.bvsd.org/projects/Eisenhower/Lists/DAT Related Resources/DispForm.aspx?ID=5https://bond.bvsd.org/projects/Eisenhower/Lists/DAT Related Resources/DispForm.aspx?ID=5{28e838a4-8015-4177-ac17-2576b5d1e514}Design Advisory Team Guidelineshttps://bond.bvsd.org/projects/Documents/DATGuidelines-Revised2015.pdf, http://bond.bvsd.org/projects/Documents/DATGuidelines-Revised2015.pdfpage

DAT Meeting Schedule

DAT meetings are open for the public to observe, and there is an opportunity for public comment at each meeting. ​​

 

 

April 5 | 3:30 - 5 p.m.https://bond.bvsd.org/projects/Eisenhower/Lists/DAT Meetings List/DispForm.aspx?ID=4https://bond.bvsd.org/projects/Eisenhower/Lists/DAT Meetings List/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}April 5 | 3:30 - 5 p.m.https://bond.bvsd.org/projects/Eisenhower/DATMeetingDocs/2017.04.05%20Eisenhower%20ES%20DAT%201%20Meeting%20Minutes%20-%20FINAL.PDF, http://bond.bvsd.org/projects/Eisenhower/DATMeetingDocs/2017.04.05%20Eisenhower%20ES%20DAT%201%20Meeting%20Minutes%20-%20FINAL.PDF
April 19 | 3:30 - 5 p.m.https://bond.bvsd.org/projects/Eisenhower/Lists/DAT Meetings List/DispForm.aspx?ID=3https://bond.bvsd.org/projects/Eisenhower/Lists/DAT Meetings List/DispForm.aspx?ID=3{28e838a4-8015-4177-ac17-2576b5d1e514}April 19 | 3:30 - 5 p.m.https://bond.bvsd.org/projects/Eisenhower/DATMeetingDocs/2017.04.19%20Eisenhower%20ES%20DAT%202%20Meeting%20Minutes%20-%20FINAL.PDF, http://bond.bvsd.org/projects/Eisenhower/DATMeetingDocs/2017.04.19%20Eisenhower%20ES%20DAT%202%20Meeting%20Minutes%20-%20FINAL.PDF
May 3 | 3:30 - 5 p.m.https://bond.bvsd.org/projects/Eisenhower/Lists/DAT Meetings List/DispForm.aspx?ID=2https://bond.bvsd.org/projects/Eisenhower/Lists/DAT Meetings List/DispForm.aspx?ID=2{28e838a4-8015-4177-ac17-2576b5d1e514}May 3 | 3:30 - 5 p.m.https://bond.bvsd.org/projects/Eisenhower/DATMeetingDocs/2017.05.03%20Eisenhower%20ES%20DAT%203%20Meeting%20Minutes%20-%20DRAFT.PDF, http://bond.bvsd.org/projects/Eisenhower/DATMeetingDocs/2017.05.03%20Eisenhower%20ES%20DAT%203%20Meeting%20Minutes%20-%20DRAFT.PDF
June 7 | 3:30 - 5 p.m.https://bond.bvsd.org/projects/Eisenhower/Lists/DAT Meetings List/DispForm.aspx?ID=6https://bond.bvsd.org/projects/Eisenhower/Lists/DAT Meetings List/DispForm.aspx?ID=6{28e838a4-8015-4177-ac17-2576b5d1e514}June 7 | 3:30 - 5 p.m.https://bond.bvsd.org/projects/Eisenhower/DATMeetingDocs/2017.06.07%20Eisenhower%20ES%20DAT%204%20Meeting%20Minutes%20-%20FINAL.PDF, http://bond.bvsd.org/projects/Eisenhower/DATMeetingDocs/2017.06.07%20Eisenhower%20ES%20DAT%204%20Meeting%20Minutes%20-%20FINAL.PDF

Timeline

 

 

Schematic Designhttps://bond.bvsd.org/projects/Eisenhower/Lists/Project Timeline/DispForm.aspx?ID=4https://bond.bvsd.org/projects/Eisenhower/Lists/Project Timeline/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}Schematic DesignMay 2017Completeinfo
Design Developmenthttps://bond.bvsd.org/projects/Eisenhower/Lists/Project Timeline/DispForm.aspx?ID=3https://bond.bvsd.org/projects/Eisenhower/Lists/Project Timeline/DispForm.aspx?ID=3{28e838a4-8015-4177-ac17-2576b5d1e514}Design DevelopmentJuly 2017Completeinfo
Construction Documentshttps://bond.bvsd.org/projects/Eisenhower/Lists/Project Timeline/DispForm.aspx?ID=2https://bond.bvsd.org/projects/Eisenhower/Lists/Project Timeline/DispForm.aspx?ID=2{28e838a4-8015-4177-ac17-2576b5d1e514}Construction DocumentsOct. 2017Completeinfo
Constructionhttps://bond.bvsd.org/projects/Eisenhower/Lists/Project Timeline/DispForm.aspx?ID=1https://bond.bvsd.org/projects/Eisenhower/Lists/Project Timeline/DispForm.aspx?ID=1{28e838a4-8015-4177-ac17-2576b5d1e514}ConstructionJune - Aug. 2018In Progresssuccess

Images

    There are no items to show in this view of the "Construction Images" list.

    Scope of Work

    Facility Condition

    • Exterior building improvements such as repair/replace windows and doors, repair masonry and paint
    • Replace roof
    • Restroom renovations
    • Improvements to interior finishes such as carpet, flooring, ceiling tile and paint
    • Asbestos abatement
    • Electrical system improvements
    • Repair/replace fixtures and equipment such as casework and kitchen equipment
    • Site improvements such as paving and landscaping
    • HVAC system improvements
    • Audio enhancement in every classroom**

    Program Compatibility 

    • Renovations to address sound issues in open classrooms
    • Provide adequate Special Education space
    • Enlarge music storage
    • Provide space for full-day kindergarten
    • Provide space for preschool

    Health and Physical Development

    • Upgrade playground equipment and surfacing

    Safety and Security

    • Install camera/intercom security system
    • Install electronic security controls
    • Redesign main entry to provide more control over visitor access

    Sustainability

    • Upgrade HVAC controls
    • Replace aged boilers with efficient condensing type
    • Conduct retro-commissioning and repairs

    Innovation

    Eisenhower Elementary School is eligible to receive up to $200,000 in additional funds to implement facility improvements that support innovative teaching methods.

    ** Not included in project budget