District-wide Support Campushttps://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=4https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}District-wide Support Campus6500 East Arapahoe Road Boulder, CO 80303www.bvsd.org720-561-5062Phase 1, 2, 31963<img alt="" src="/PublishingImages/PPT-blue-book-alone.gif" style="BORDER:0px solid;" />See breakout by project under Scope of WorkN/A

Latest Updates

Education Center Employee and Visitor Access During Construction

Construction Progress

  

Construction of the foundation and elevator shaft are underway for the new wing of the Education Center.


 

 

Culinary Centerhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=51https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=51{28e838a4-8015-4177-ac17-2576b5d1e514}Culinary CenterDecember 2019 | The building is fully enclosed with the exterior walls and roof in place. Interior construction is underway. The project is on track to be complete next spring with the kitchen operational for the 2020-21 school year.
Administrative Offices and Professional Development Centerhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=50https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=50{28e838a4-8015-4177-ac17-2576b5d1e514}Administrative Offices and Professional Development CenterDecember 2019 | Work on the foundation for the new wing is underway. Drilling and pouring concrete for caissons is underway. Please see the map above for the adjusted logistics during construction and be aware that parking is limited. Thank you for your patience and understanding.
Check out the plans for the Ed Center renovation!https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=29https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=29{28e838a4-8015-4177-ac17-2576b5d1e514}Check out the plans for the Ed Center renovation!https://drive.google.com/file/d/0B6ygZ9WZL67uNUNQeDhEbHFzQ09lSGJXeDRKQ0RmaG5SOW1z/view?usp=sharing, https://bond.bvsd.org/projects/DWSC/Documents/20181125%20BVSD%20Open%20House%20PRINTS-sm.pdf

 

 

Central Kitchenhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=48https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=48{28e838a4-8015-4177-ac17-2576b5d1e514}Central KitchenOctober 2019 | The structure is steadily moving toward being fully enclosed with the exterior walls and roof in place. Windows and doors will be installed in the coming weeks. The project is on track to be complete next spring with the kitchen operational for the 2020-21 school year.
Warehouse, Administrative Offices, and Professional Development Centerhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=49https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=49{28e838a4-8015-4177-ac17-2576b5d1e514}Warehouse, Administrative Offices, and Professional Development CenterOctober 2019 | The east half of the Ed Center has been demolished and work on the foundation for the new wing is underway. Drilling and pouring concrete for caissons will occur in the first half of November, weather permitting. Please see the map above for the adjusted logistics during construction and be aware that parking is limited. Thank you for your patience and understanding.
Warehouse, Administrative Offices, and Professional Development Centerhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=46https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=46{28e838a4-8015-4177-ac17-2576b5d1e514}Warehouse, Administrative Offices, and Professional Development CenterSeptember 2019 | Demolition of the east wing has started and should take about a month to complete. The PDC/board room is open and hosting meetings. Visitors to the Education Center should use the driveway west of the main traffic light entrance and park on the west side of the building.
Central Kitchenhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=47https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=47{28e838a4-8015-4177-ac17-2576b5d1e514}Central KitchenSeptember 2019 | Exterior walls have been constructed and the roof will be attached in the coming weeks. The project is on track for completion next spring.
Central Kitchenhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=26https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=26{28e838a4-8015-4177-ac17-2576b5d1e514}Central KitchenNovember 2018 | On October 17, 2018, the Citizens' Bond Oversight Committee approved augmenting the Central Kitchen project budget with $2.8 million of bond premium funds to meet construction cost estimates. Construction is expected to begin in the coming weeks. https://docs.google.com/presentation/d/1AnF8Xmyf0rp7hvj01nzNwjt2jIUu8rd8gx6y6-X4rQo/edit?usp=sharing, https://docs.google.com/presentation/d/1AnF8Xmyf0rp7hvj01nzNwjt2jIUu8rd8gx6y6-X4rQo/edit?usp=sharing
Warehouse, Administrative Offices and Professional Learning Centerhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=27https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=27{28e838a4-8015-4177-ac17-2576b5d1e514}Warehouse, Administrative Offices and Professional Learning CenterNovember 2018 | The architects are finalizing the schematic design. Construction is anticipated to begin in spring/summer of 2019. Boulder Commercial Interiors has been selected as the furniture vendor and is working with the Furniture Steering Committee to plan and select furniture. A relocation consultant has been hired to develop transition plans. https://docs.google.com/document/d/1xNaOjZX7EDqBBVa6sHVYM8yz8y01KLcbIM33W9XRZyA/edit?usp=sharing, https://docs.google.com/document/d/1xNaOjZX7EDqBBVa6sHVYM8yz8y01KLcbIM33W9XRZyA/edit?usp=sharing
Ed Center Information Session | March 5, 3:30-4:30https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=34https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=34{28e838a4-8015-4177-ac17-2576b5d1e514}Ed Center Information Session | March 5, 3:30-4:30An information session will be held March 5, 3:30-4:30 p.m. in the PDC Aspen room. Project team members (architect, furniture vendor, contractor, relocation specialist) will give a presentation at 3:30 and be available to answer questions afterward. Meeting materials will be emailed to staff following the meeting.
Central Kitchenhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=35https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=35{28e838a4-8015-4177-ac17-2576b5d1e514}Central KitchenMarch 2019 | The project team has been working to relocate fiber optic and utility lines. Activity will pick up in March, and we will likely see the demolition of the Transportation building.
Warehouse, Administrative Offices, and Professional Learning Centerhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=33https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=33{28e838a4-8015-4177-ac17-2576b5d1e514}Warehouse, Administrative Offices, and Professional Learning CenterMarch 2019 | The Ed Center renovation plans are moving into the final stages of design. The project is on track to start construction this spring and be complete by December 2020. The furniture committee has worked with the furniture vendor to develop several office and cubicle layout options. Prototype layouts will be set up in various locations in the Ed Center in the coming weeks for staff to see. The selected color palette also will be on display with the layouts. Follow the link for more information. https://docs.google.com/document/d/1PHTWvnZCTCeIp7O_twwCntLwZftyTbEdBiWsHg9kR40/edit?usp=sharing, https://docs.google.com/document/d/1PHTWvnZCTCeIp7O_twwCntLwZftyTbEdBiWsHg9kR40/edit?usp=sharing
Education Center Schematic Design Gallery Walk | Nov. 27, 3-5 p.m., Building for Student Successhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=28https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=28{28e838a4-8015-4177-ac17-2576b5d1e514}Education Center Schematic Design Gallery Walk | Nov. 27, 3-5 p.m., Building for Student SuccessThe schematic design for the major renovation of the Education Center will be on display at the Building for Student Success offices at Arapahoe Campus for employees to view and provide feedback. Follow the link for a map. https://drive.google.com/file/d/0B9YXu0BD9JOTY180Zml4czBhWms/view?usp=sharing, https://drive.google.com/file/d/0B9YXu0BD9JOTY180Zml4czBhWms/view?usp=sharing
Central Kitchenhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=37https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=37{28e838a4-8015-4177-ac17-2576b5d1e514}Central KitchenApril 2019 | The project team celebrated the official ground-breaking for the new Central Kitchen this month! Crews are busily preparing the site for utility installation and constructing the foundation.
Warehouse, Administrative Offices, and Professional Learning Centerhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=38https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=38{28e838a4-8015-4177-ac17-2576b5d1e514}Warehouse, Administrative Offices, and Professional Learning CenterApril 2019 | Construction-related activity is picking up inside and outside the Ed Center. Over Spring Break, the old Transportation facility was demolished and JHL Construction has started to construct the foundation for the new Central Kitchen. The project team is still on track to start construction at the Ed Center on June 3. JHL will expand the construction area to include the Ed Center the last week of May. Approximately half of the site will become an active construction area, and as such, there will be significant temporary changes to pedestrian and vehicle circulation, as well as parking. Site logistic plans are being developed and will be shared in the coming weeks. Check back for updates.
Ed Center will be closed May 29 - June 2https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=39https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=39{28e838a4-8015-4177-ac17-2576b5d1e514}Ed Center will be closed May 29 - June 2Due to moving activity, the Education Center will be closed to staff and the public May 29 - June 2, 2019. Staff are asked to find alternative work locations for these days. The building will reopen to the public June 3.
Board meetings will be held at the Superior Town Hall in June and Augusthttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=40https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=40{28e838a4-8015-4177-ac17-2576b5d1e514}Board meetings will be held at the Superior Town Hall in June and AugustDue to construction at the Education Center, BVSD Board of Education meetings will be relocated to Superior Town Hall (124 E Coal Creek Dr.) over the summer (June 11, 25 and Aug. 13, 27).
Warehouse, Administrative Offices, and Professional Learning Centerhttps://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=42https://bond.bvsd.org/projects/DWSC/Lists/Latest Updates/DispForm.aspx?ID=42{28e838a4-8015-4177-ac17-2576b5d1e514}Warehouse, Administrative Offices, and Professional Learning CenterMay 2019 | The project is still on track to start major construction on June 3. The first stage of construction this summer will involve demolition of the existing east wing of the building. A new two-story structure will replace this area of the building. Also this summer, the Professional Development Center will be renovated to accommodate board meetings (including a broadcast booth) in addition to regular meeting use. Once construction of the new wing is complete, staff will move into the new space and renovations will take place in the remainder of the building. Staff members currently housed in the section of the building that will be demolished will be temporarily relocated to other parts of the Ed Center or offsite locations.

Project Details

Project Team
Project Manager

 

 

Steve Schumacherhttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=7{28e838a4-8015-4177-ac17-2576b5d1e514}Steve Schumachersteve.schumacher@bvsd.org720-561-5270mailto:steve.schumacher@bvsd.org, mailto:steve.schumacher@bvsd.org

Architect

 

 

RNL https://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=16{28e838a4-8015-4177-ac17-2576b5d1e514}RNL http://www.rnldesign.com/, http://www.rnldesign.com/

Contractor

 

 

JHLhttps://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=39{28e838a4-8015-4177-ac17-2576b5d1e514}JHLhttp://www.jhlconstructors.com/, http://www.jhlconstructors.com/

Related Resources

 

 

Educational Facilities Master Planhttps://bond.bvsd.org/projects/DWSC/Lists/Related Resources/DispForm.aspx?ID=4https://bond.bvsd.org/projects/DWSC/Lists/Related Resources/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}Educational Facilities Master Planhttps://bond.bvsd.org/masterplan/Documents/EdFacilityMasterPlan.pdf#page=79, http://bond.bvsd.org/masterplan/Documents/EdFacilityMasterPlan.pdf#page=79page

Details
Project Budget

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=4https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}See breakout by project under Scope of Work

Innovation Budget

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=4https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}N/A

Bond Expenditures

 

 

https://bond.bvsd.org/financial/Documents/CurrentProjectExpenditures.pdf, Project Expenditures

Project Expenditures

 

 

https://bond.bvsd.org/financial/Documents/CurrentProjectExpenditures.pdf, Project Expenditures

Sustainability Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=4https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}<div class="ExternalClass38CA90646CC444108742C21BD5AC2864"><div>Under development</div></div>

Energy Efficiency/Green Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=4https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}<div class="ExternalClass74CD831D02F9462EA5754D366540EDB0"><div>Under development</div></div>

Educational Innovation Features

 

 

https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=4https://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}<div class="ExternalClassCE157B45ACF84793A8B21392C8F314E8"><div>Under development</div></div>

Design Advisory Team

The Design Advisory Team (DAT) team includes district staff members who will work with the architects to develop the design for the project.​ 

​Staff

Rob Anderson, Superintendent
Laura Shafer, Executive Assistant to the Superintendent and Board of Education
Sam Messier, Assistant Superintendent of Instructional Services and Equity
Rob Price, Assistant Superintendent of Operational Services
Kim Mann, Executive Assistant to the Assistant Superintendent of Operational Services
Susan Cousins, Bond Communications Specialist
Mike Gradoz, Assistant Superintendent of Human Resources
Vivian Campbell, Human Resources Manager
Randy Barber, Chief Communications Officer
Andrew Moore, Chief Information Officer
Robbyn Fernandez, Assistant Superintendent of Schools - Elementary

Parents

​​Community

Related Resources

 

 

DAT Guidelines - Revised 2015https://bond.bvsd.org/projects/DWSC/Lists/DAT Related Resources/DispForm.aspx?ID=4https://bond.bvsd.org/projects/DWSC/Lists/DAT Related Resources/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}DAT Guidelines - Revised 2015https://bond.bvsd.org/projects/Documents/DATGuidelines-Revised2015.pdf, http://bond.bvsd.org/projects/Documents/DATGuidelines-Revised2015.pdfdownload

DAT Meeting Schedule

DAT meetings are open for the public to observe, and there is an opportunity for public comment at each meeting.  Additional meetings (noted below) will be held for the Ed Center renovation project. 

 

 

Education Center DAT | June 6, 2018, 3:30 - 5:30 p.m.https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=18https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=18{28e838a4-8015-4177-ac17-2576b5d1e514}Education Center DAT | June 6, 2018, 3:30 - 5:30 p.m.https://bond.bvsd.org/projects/DWSC/DATMeetingDocs/2018_0606%20DAT-1%20Admin%20Meeting%20Minutes.pdf, https://bond.bvsd.org/projects/DWSC/DATMeetingDocs/2018_0606%20DAT-1%20Admin%20Meeting%20Minutes.pdfhttps://bond.bvsd.org/projects/DWSC/DATMeetingDocs/20180606-DAT%201%20BVSD%20Admin%20Workspace-FINAL%20WEB.pdf, https://bond.bvsd.org/projects/DWSC/DATMeetingDocs/20180606-DAT%201%20BVSD%20Admin%20Workspace-FINAL%20PRINTreduced.pdf
Education Center Department Heads | June 13, 2018https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=19https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=19{28e838a4-8015-4177-ac17-2576b5d1e514}Education Center Department Heads | June 13, 2018
Education Center Department Heads | June 27, 2018https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=20https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=20{28e838a4-8015-4177-ac17-2576b5d1e514}Education Center Department Heads | June 27, 2018
Education Center DAT | August 1, 2018, 3:30 - 5:30 p.m.https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=21https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=21{28e838a4-8015-4177-ac17-2576b5d1e514}Education Center DAT | August 1, 2018, 3:30 - 5:30 p.m.https://bond.bvsd.org/projects/DWSC/DATMeetingDocs/2018_0803%20DAT-2%20Meeting%20Minutes.pdf, https://bond.bvsd.org/projects/DWSC/DATMeetingDocs/2018_0803%20DAT-2%20Meeting%20Minutes.pdf
Education Center Board Room Work Session | September 18, 2018https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=26https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=26{28e838a4-8015-4177-ac17-2576b5d1e514}Education Center Board Room Work Session | September 18, 2018
Education Center Department Heads | November 8, 2018https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=25https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=25{28e838a4-8015-4177-ac17-2576b5d1e514}Education Center Department Heads | November 8, 2018
Education Center Board Room Work Session | November 27, 2018https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=27https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=27{28e838a4-8015-4177-ac17-2576b5d1e514}Education Center Board Room Work Session | November 27, 2018
Education Center DAT | January 10, 2019 | 2:30 - 4 p.m. https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=28https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=28{28e838a4-8015-4177-ac17-2576b5d1e514}Education Center DAT | January 10, 2019 | 2:30 - 4 p.m. https://bond.bvsd.org/projects/DWSC/DATMeetingDocs/20190110%20DAT3%20PRESENTATION-reduced.pdf, https://bond.bvsd.org/projects/DWSC/DATMeetingDocs/20190110%20DAT3%20PRESENTATION-reduced.pdf
Transportation DAT June 3, 2016https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=10https://bond.bvsd.org/projects/DWSC/Lists/DAT Meetings List/DispForm.aspx?ID=10{28e838a4-8015-4177-ac17-2576b5d1e514}Transportation DAT June 3, 2016https://bond.bvsd.org/projects/DWSC/DATMeetingDocs/2016-06-02%20BVSD%20BUS%20Meeting%20Minutes.pdf, http://bond.bvsd.org/projects/DWSC/DATMeetingDocs/2016-06-02%20BVSD%20BUS%20Meeting%20Minutes.pdfhttps://bond.bvsd.org/projects/DWSC/DATMeetingDocs/2016-06-01_BVSD_Adj%20Site%20Entry_Drawing%20Notes.pdf, http://bond.bvsd.org/projects/DWSC/DATMeetingDocs/2016-06-01_BVSD_Adj%20Site%20Entry_Drawing%20Notes.pdf

Timeline

 

 

Ed Center Schematic Designhttps://bond.bvsd.org/projects/DWSC/Lists/Project Timeline/DispForm.aspx?ID=8https://bond.bvsd.org/projects/DWSC/Lists/Project Timeline/DispForm.aspx?ID=8{28e838a4-8015-4177-ac17-2576b5d1e514}Ed Center Schematic DesignNovember 2018Completesuccess
Ed Center Design Developmenthttps://bond.bvsd.org/projects/DWSC/Lists/Project Timeline/DispForm.aspx?ID=9https://bond.bvsd.org/projects/DWSC/Lists/Project Timeline/DispForm.aspx?ID=9{28e838a4-8015-4177-ac17-2576b5d1e514}Ed Center Design DevelopmentJanuary 2019Completesuccess
Ed Center Construction Documentshttps://bond.bvsd.org/projects/DWSC/Lists/Project Timeline/DispForm.aspx?ID=10https://bond.bvsd.org/projects/DWSC/Lists/Project Timeline/DispForm.aspx?ID=10{28e838a4-8015-4177-ac17-2576b5d1e514}Ed Center Construction DocumentsApril 2019Completesuccess
Ed Center Constructionhttps://bond.bvsd.org/projects/DWSC/Lists/Project Timeline/DispForm.aspx?ID=6https://bond.bvsd.org/projects/DWSC/Lists/Project Timeline/DispForm.aspx?ID=6{28e838a4-8015-4177-ac17-2576b5d1e514}Ed Center ConstructionSpring 2018 - Aug. 2020In Progressinfo

Images

​​    Hover over the image and scroll down.

    There are no items to show in this view of the "Construction Images" list.

    Scope of Work

    The Educational Master Plan includes the following projects to support and improve district systems and services provided at the Education Center:

    Transportation
    Estimated Project Budget: $24,097,193
    • Demolish the existing district Transportation offices, bus parking, and vehicle washing facility and replace with a new structure
    • Renovate the existing fleet maintenance facility
    Technology Training Center, administrative offices, and warehouse
    Estimated Project Budget: $26,913,446
    • Expand the existing Professional Development Center to provide additional space for student and staff technology training
    • Partially demolish the existing building and replace with a new structure on a smaller footprint to provide more parking
    • Modernize workspaces
    • Provide adequate space to accommodate staff currently working at another location
    • Provide secure after-hours access to meeting spaces
    • Improve public access for visitors
    • Renovate existing warehouse space
    District Kitchen
    Estimated Project Budget: $16,066,659
    • Renovate existing space to create a District Kitchen