BCSIS and High Peakshttp://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60{28e838a4-8015-4177-ac17-2576b5d1e514}BCSIS and High Peaks3995 East Aurora Avenue Boulder, CO 80303http://www.bvsd.org/elementary/Pages/default.aspx720.561.6500Phase 21963<img alt="" src="/projects/Project%20Profile%20Images/BCSIS-HP-ES-photo-300x300.JPG" style="BORDER:0px solid;" />$6,702,090$200,000 included in budget

Latest Updates

 

 

May 2017http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=16http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=16{28e838a4-8015-4177-ac17-2576b5d1e514}May 2017The final construction cost estimate the district received from the general contractor in April exceeds the project budget by $1.6 M, and the project has been postponed until next summer (May-August 2018). The district will bid the project again in the fall and anticipates pricing will be more competitive at that time. The project team is evaluating the possibility of moving forward with some discrete elements of the project this summer. https://docs.google.com/document/d/1WglCtmYio509mEa63YIbfDuJH95VgRMJCx15T5R0UkE/edit?usp=sharing, https://docs.google.com/document/d/1WglCtmYio509mEa63YIbfDuJH95VgRMJCx15T5R0UkE/edit?usp=sharing

 

 

September 2016http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=10http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=10{28e838a4-8015-4177-ac17-2576b5d1e514}September 2016The design phase for the building renovation project is set to kick-off in September. A Design Advisory Team (DAT) will be selected to work with the architect to develop the project design. Check back for the DAT meeting schedule and minutes.
October 2016http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=11http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=11{28e838a4-8015-4177-ac17-2576b5d1e514}October 2016The professional design team is working with the Design Advisory Team to develop a schematic design.
This project is scheduled to begin in Phase 2. http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=8http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=8{28e838a4-8015-4177-ac17-2576b5d1e514}This project is scheduled to begin in Phase 2.
February 2017http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=12http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=12{28e838a4-8015-4177-ac17-2576b5d1e514}February 2017The project team is working with the design advisory team on Design Development. For more information, see the DAT meeting minutes below. Construction is planned to begin in March.
Construction Kick-off Postcard to Neighborshttp://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=15http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=15{28e838a4-8015-4177-ac17-2576b5d1e514}Construction Kick-off Postcard to Neighborshttp://bond.bvsd.org/projects/BCSIS-HP/Documents/BCSIS%20High%20Peaks%20construction%20start%20notification%20postcard%20text%20-%20neighbor%20web.pdf, http://bond.bvsd.org/projects/BCSIS-HP/Documents/BCSIS%20High%20Peaks%20construction%20start%20notification%20postcard%20text%20-%20neighbor%20web.pdf
April 2017http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=13http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=13{28e838a4-8015-4177-ac17-2576b5d1e514}April 2017The project team is preparing for construction to begin in May.
Construction Kick-off Letter to Parentshttp://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=14http://bond.bvsd.org/projects/BCSIS-HP/Lists/Latest Updates/DispForm.aspx?ID=14{28e838a4-8015-4177-ac17-2576b5d1e514}Construction Kick-off Letter to Parentshttps://docs.google.com/document/d/1QlPG7g87NPwmo3naLQNucQTENIb2UvhMEai96OyVOY4/edit?usp=sharing, https://docs.google.com/document/d/1QlPG7g87NPwmo3naLQNucQTENIb2UvhMEai96OyVOY4/edit?usp=sharing

Project Details

Project Team
Project Manager

 

 

Katheryn Zeebhttp://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=44{28e838a4-8015-4177-ac17-2576b5d1e514}Katheryn Zeebkatheryn.zeeb@bvsd.org720.561.5109

Architect

 

 

LKA Partnershttp://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=45{28e838a4-8015-4177-ac17-2576b5d1e514}LKA Partnershttp://markyoungconstruction.com/, http://markyoungconstruction.com/

Contractor

 

 

PCL Construction http://bond.bvsd.org/projects/Lists/Master Contacts/DispForm.aspx?ID=48{28e838a4-8015-4177-ac17-2576b5d1e514}PCL Construction

Related Resources

 

 

Educational Facilities Master Planhttp://bond.bvsd.org/projects/BCSIS-HP/Lists/Related Resources/DispForm.aspx?ID=5http://bond.bvsd.org/projects/BCSIS-HP/Lists/Related Resources/DispForm.aspx?ID=5{28e838a4-8015-4177-ac17-2576b5d1e514}Educational Facilities Master Planhttp://bond.bvsd.org/masterplan/Documents/EdFacilityMasterPlan.pdf#page=25, http://bond.bvsd.org/masterplan/Documents/EdFacilityMasterPlan.pdf#page=25page

Details
Project Budget

 

 

http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60{28e838a4-8015-4177-ac17-2576b5d1e514}$6,702,090

Innovation Budget

 

 

http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60{28e838a4-8015-4177-ac17-2576b5d1e514}$200,000 included in budget

Bond Expenditures

 

 

BCSIS and High Peakshttp://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60{28e838a4-8015-4177-ac17-2576b5d1e514}BCSIS and High Peakshttp://bond.bvsd.org/financial/Documents/CurrentProgramExpenditures.pdf, Bond Program Expenditures

Project Expenditures

 

 

http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60{28e838a4-8015-4177-ac17-2576b5d1e514}http://bond.bvsd.org/financial/Documents/CurrentProjectExpenditures.pdf, Project Expenditures

Sustainability Features

 

 

http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60{28e838a4-8015-4177-ac17-2576b5d1e514}<div class="ExternalClassA31B7CBD84F5411EA346A40776A93294"><div>Under development<br></div></div>

Energy Efficiency/Green Features

 

 

http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60{28e838a4-8015-4177-ac17-2576b5d1e514}<div class="ExternalClass6D18EFBEF7724CCE80DD61B953B0C21E"><p>Under development<br></p></div>

Educational Innovation Features

 

 

http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60http://bond.bvsd.org/projects/Lists/ProjectsProfiles/DispForm.aspx?ID=60{28e838a4-8015-4177-ac17-2576b5d1e514}<div class="ExternalClassDFE1EBC9E1874CC68268120197770177"><p><strong>BCSIS Innovation Project<br></strong>The school plans to create a flexible space that will be used for a variety of activities such as mindfulness work, drama, Socratic Seminars, presentations, movement and dance, and arts integration. This space will be a room that inspires creativity.  <strong style="text-decoration:underline;color:#ff9933;"><a href="/educational-innovation/Pages/BCSIS-Innovation-Project.aspx"><span style="color:#ff9933;text-decoration:underline;">Learn more</span></a></strong><br></p><p><strong>High Peaks Innovation Project<br></strong>High Peaks plans to use its Innovation funds for three purposes: 1) An intermediate innovation space 2) New classroom furniture for primary classrooms 3) Library Innovations  <span style="text-decoration:underline;color:#ff9933;"><strong style="color:#ff9933;text-decoration:underline;"><a href="/educational-innovation/Pages/High-Peaks-Innovation-Project.aspx"><span style="color:#ff9933;text-decoration:underline;">Learn more</span></a></strong></span><br></p></div>

Design Advisory Team

​The Design Advisory Team (DAT) team includes teachers, staff, parents and community members who will work with the architects to develop the design for the project.​

Staff 

Phil Katsampes, BCSIS Principal
Sabine Smead, BCSIS Teacher
Kiley Lewis, BCSIS Teacher

Jeannie Tynecki, High Peaks Principal
Zach Fink, High Peaks Teacher
Lindsey Pisano, High Peaks Teacher

Lisa Gefke, Office Staff
Rachel Horvath, Preschool Teacher


Parents
Jill Iwaskow, BCSIS
Valerie Seiler, High Peaks

  
​​Community​
Related Resources

 

 

Design Advisory Team Guidelineshttp://bond.bvsd.org/projects/BCSIS-HP/Lists/DAT Related Resources/DispForm.aspx?ID=5http://bond.bvsd.org/projects/BCSIS-HP/Lists/DAT Related Resources/DispForm.aspx?ID=5{28e838a4-8015-4177-ac17-2576b5d1e514}Design Advisory Team Guidelineshttp://bond.bvsd.org/projects/Documents/DATGuidelines-Revised2015.pdf, http://bond.bvsd.org/projects/Documents/DATGuidelines-Revised2015.pdfpage

DAT Meeting Schedule

DAT meetings are open for the public to observe, and there is an opportunity for public comment at each meeting. ​​

 

 

September 22 | 2:45 - 4:15 p.m.http://bond.bvsd.org/projects/BCSIS-HP/Lists/DAT Meetings List/DispForm.aspx?ID=1http://bond.bvsd.org/projects/BCSIS-HP/Lists/DAT Meetings List/DispForm.aspx?ID=1{28e838a4-8015-4177-ac17-2576b5d1e514}September 22 | 2:45 - 4:15 p.m.http://bond.bvsd.org/projects/BCSIS-HP/DATMeetingDocs/DAT1%20CR%202016%2009%2022%20245PM.pdf, http://bond.bvsd.org/projects/BCSIS-HP/DATMeetingDocs/DAT1%20CR%202016%2009%2022%20245PM.pdf
October 4 | 2:45 - 4:15 p.m.http://bond.bvsd.org/projects/BCSIS-HP/Lists/DAT Meetings List/DispForm.aspx?ID=2http://bond.bvsd.org/projects/BCSIS-HP/Lists/DAT Meetings List/DispForm.aspx?ID=2{28e838a4-8015-4177-ac17-2576b5d1e514}October 4 | 2:45 - 4:15 p.m.http://bond.bvsd.org/projects/BCSIS-HP/DATMeetingDocs/DAT2%20CR%202016%2010%2004%20245PM.pdf, http://bond.bvsd.org/projects/BCSIS-HP/DATMeetingDocs/DAT2%20CR%202016%2010%2004%20245PM.pdf
October 12 | 2:15 - 4:30 p.m.http://bond.bvsd.org/projects/BCSIS-HP/Lists/DAT Meetings List/DispForm.aspx?ID=3http://bond.bvsd.org/projects/BCSIS-HP/Lists/DAT Meetings List/DispForm.aspx?ID=3{28e838a4-8015-4177-ac17-2576b5d1e514}October 12 | 2:15 - 4:30 p.m.http://bond.bvsd.org/projects/BCSIS-HP/DATMeetingDocs/DAT3%20CR%202016%2010%2012%20215PM.pdf, http://bond.bvsd.org/projects/BCSIS-HP/DATMeetingDocs/DAT3%20CR%202016%2010%2012%20215PM.pdf
October 26, 2016 | 2:15 - 4:30 p.m.http://bond.bvsd.org/projects/BCSIS-HP/Lists/DAT Meetings List/DispForm.aspx?ID=4http://bond.bvsd.org/projects/BCSIS-HP/Lists/DAT Meetings List/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}October 26, 2016 | 2:15 - 4:30 p.m.http://bond.bvsd.org/projects/BCSIS-HP/DATMeetingDocs/DAT3%20CR%202016%2010%2012%20215PMweb.pdf, http://bond.bvsd.org/projects/BCSIS-HP/DATMeetingDocs/DAT3%20CR%202016%2010%2012%20215PMweb.pdf
November 1 | 2:15 - 4:45 p.m.http://bond.bvsd.org/projects/BCSIS-HP/Lists/DAT Meetings List/DispForm.aspx?ID=5http://bond.bvsd.org/projects/BCSIS-HP/Lists/DAT Meetings List/DispForm.aspx?ID=5{28e838a4-8015-4177-ac17-2576b5d1e514}November 1 | 2:15 - 4:45 p.m.http://bond.bvsd.org/projects/BCSIS-HP/DATMeetingDocs/DAT5%20CR%202016%2011%2001%20215PMweb.pdf, http://bond.bvsd.org/projects/BCSIS-HP/DATMeetingDocs/DAT5%20CR%202016%2011%2001%20215PMweb.pdf

Timeline

 

 

Schematic Designhttp://bond.bvsd.org/projects/BCSIS-HP/Lists/Project Timeline/DispForm.aspx?ID=1http://bond.bvsd.org/projects/BCSIS-HP/Lists/Project Timeline/DispForm.aspx?ID=1{28e838a4-8015-4177-ac17-2576b5d1e514}Schematic DesignNov. 2016Completeinfo
Design Developmenthttp://bond.bvsd.org/projects/BCSIS-HP/Lists/Project Timeline/DispForm.aspx?ID=2http://bond.bvsd.org/projects/BCSIS-HP/Lists/Project Timeline/DispForm.aspx?ID=2{28e838a4-8015-4177-ac17-2576b5d1e514}Design DevelopmentDec. 2016Completeinfo
Construction Documentshttp://bond.bvsd.org/projects/BCSIS-HP/Lists/Project Timeline/DispForm.aspx?ID=3http://bond.bvsd.org/projects/BCSIS-HP/Lists/Project Timeline/DispForm.aspx?ID=3{28e838a4-8015-4177-ac17-2576b5d1e514}Construction DocumentsFeb. 2017Completeinfo
Constructionhttp://bond.bvsd.org/projects/BCSIS-HP/Lists/Project Timeline/DispForm.aspx?ID=4http://bond.bvsd.org/projects/BCSIS-HP/Lists/Project Timeline/DispForm.aspx?ID=4{28e838a4-8015-4177-ac17-2576b5d1e514}ConstructionMar. - Aug. 2017Not Startedsuccess

Images

​​    Check back here for photos of the project!
    There are no items to show in this view of the "Construction Images" list.

    Scope of Work

    ​Facility Condition

    • Roof repair/replacement
    • Repair/replace exterior windows and doors
    • Improvements to interior finishes such as ceilings, wall tile and paint
    • HVAC improvements
    • Plumbing  improvements
    • Fire alarm and communications upgrades
    • Repair/replace fixtures such as casework and countertops
    • Site improvements such as drainage, fencing, paving irrigation, landscaping and playfield renovation
    • Asbestos abatement
    • Improve preschool drop-off
    • Audio enhancement in every classroom**

    Program Compatibility Assessment

    • Provide teacher lounge/work room
    • Provide additional storage
    • Provide adequate space for full-day kindergarten**
    • Provide adequate space for preschool**

    Health and Physical Development

    • Upgrade playground equipment and surface materials
    • Renovate preschool playground

    Safety and Security

    • Install camera/intercom security system
    • Install electronic security controls
    • Install security partitions

    Sustainability​

    • Conduct retro-commissioning and repairs
    • Upgrade HVAC controls
    • Replace aged boilers with more efficient condensing type

    Innovation​

    BCSIS/High Peaks are eligible to receive up to $200,000 in additional funds to implement facility improvements that support innovative teaching methods. ​

    ** Not included in estimated school budget.